III SPP 3/09 AI generated

Supreme Court dismisses appeal for delay filed after final judgment becomes legally binding.

Case Number III SPP 3/09
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Supreme Court rejected a complaint filed by the appellant against the excessive length of proceedings before the Court of Appeal in Warsaw. Although the appellant argued that the court failed to issue a written judgment within the statutory timeframe, violating his constitutional right to a speedy trial, the court noted that the appeal had already been dismissed by a final, binding judgment. The court ruled that once a case is legally concluded, no further proceedings can occur, making it impossible to determine procedural delay or issue recommendations for a new trial.

Legislator headnote

AI generated

Art. 387 § 2 k.p.c.; Art. 45 ust. 1 Konstytucji: A complaint for delay in proceedings is inadmissible if filed after the final judgment has become legally binding, as the proceedings have already concluded and no further action can be taken.

Keywords

AI generated
inadmissible appeal final judgment procedural delay speedy trial legal conclusion Supreme Court procedural law

Cited Legislation

AI generated
Art. 387 § 2 k.p.c.
Art. 45 ust. 1 Konstytucji
Art. 176 ust. 2 Konstytucji
Art. 2, 4, 8 ust. 2 ustawy
Art. 373 w związki z art. 397 § 2 k.p.c.
art. 387 § 2 k.p.c
art. 45 ust. 1 Konstytucji
art. 176 ust. 2 Konstytucji
art. 329 k.p.c
art. 397 § 2 k.p.c

Cited Case Law

AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text