Construction Lien Deadline with Successive Contracts and Final Component Delivery
Legislator summary
AI generatedThe court considered the deadline for registering a construction lien under Article 839 Para. 2 of the Civil Code when multiple, temporally separated work contracts are involved, where the lower court had ruled the three-month period had expired based on the earliest work completion. The appellate court overturned this, reasoning that repeatedly performed, similar services for the same construction project, even if under formally separate contracts taken over by a successor company, constitute a single construction work with a unified deadline, provided there is an internal functional connection, and the final delivery of a necessary component, such as a maintenance access cover essential for the reliable operation of the ventilation system, extends the completion date, thereby validating the timely filing of the lien application.
Legislator headnote
AI generatedArt. 839 Abs. 2 ZGB, Art. 839 ZGB; Construction Lien Deadline with Successive Contracts and Final Component Delivery: 2 of the Civil Code when multiple, temporally separated work contracts are involved, where the lower court had ruled the three-month period had expired based on the earliest work completion. The appellate court overturned this, reasoning that repeatedly performed, similar services for the same construction project, even if under formally separate contracts taken over by a successor company, constitute a single construction work with a unified deadline, provided there is an internal functional connection, and the final delivery of a necessary component, such as a maintenance access cover essential for the reliable operation of the ventilation system, extends the completion date, thereby validating the timely filing of the lien application.
Keywords
AI generatedCited Legislation
AI generatedCited Case Law
AI generatedRelated Decisions
AI generatedKey legal questions extracted by Legislator
AI generatedThis provision governs the deadline for registering a construction lien, which was the central issue decided by the court.
Full text
Rechtsprechung Luzern
Instanz: · Obergericht
Abteilung: · I. Kammer
Rechtsgebiet: · Sachenrecht
Entscheiddatum: · 05.12.2002
Fallnummer: · 11 02 72
LGVE: · 2002 I Nr. 22
Leitsatz: · Art. 839 Abs. 2 ZGB. Beginn der Dreimonatsfrist für die Eintragung eines Bauhandwerkerpfandrechts bei mehreren Werkverträgen.
Rechtskraft: · Diese Entscheidung ist rechtskräftig.