Construction Lien Deadline with Successive Contracts and Final Component Delivery

Case Number 11 02 72
Court / Authority
Jurisdiction Switzerland · Canton of Lucerne (CH-LU)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The court considered the deadline for registering a construction lien under Article 839 Para. 2 of the Civil Code when multiple, temporally separated work contracts are involved, where the lower court had ruled the three-month period had expired based on the earliest work completion. The appellate court overturned this, reasoning that repeatedly performed, similar services for the same construction project, even if under formally separate contracts taken over by a successor company, constitute a single construction work with a unified deadline, provided there is an internal functional connection, and the final delivery of a necessary component, such as a maintenance access cover essential for the reliable operation of the ventilation system, extends the completion date, thereby validating the timely filing of the lien application.

Legislator headnote

AI generated

Art. 839 Abs. 2 ZGB, Art. 839 ZGB; Construction Lien Deadline with Successive Contracts and Final Component Delivery: 2 of the Civil Code when multiple, temporally separated work contracts are involved, where the lower court had ruled the three-month period had expired based on the earliest work completion. The appellate court overturned this, reasoning that repeatedly performed, similar services for the same construction project, even if under formally separate contracts taken over by a successor company, constitute a single construction work with a unified deadline, provided there is an internal functional connection, and the final delivery of a necessary component, such as a maintenance access cover essential for the reliable operation of the ventilation system, extends the completion date, thereby validating the timely filing of the lien application.

Keywords

AI generated
construction contract date of filing statutory deadlines registration of legal lien deadline for payment law of obligations

Cited Legislation

AI generated

Cited Case Law

AI generated
AI generated

Key legal questions extracted by Legislator

AI generated
Art. 839 Abs. 2 ZGB

This provision governs the deadline for registering a construction lien, which was the central issue decided by the court.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Rechtsprechung Luzern

Instanz: · Obergericht

Abteilung: · I. Kammer

Rechtsgebiet: · Sachenrecht

Entscheiddatum: · 05.12.2002

Fallnummer: · 11 02 72

LGVE: · 2002 I Nr. 22

Leitsatz: · Art. 839 Abs. 2 ZGB. Beginn der Dreimonatsfrist für die Eintragung eines Bauhandwerkerpfandrechts bei mehreren Werkverträgen.

Rechtskraft: · Diese Entscheidung ist rechtskräftig.