Delivery of notices, etc.

10.

Delivery of notices, etc.

Delivery of notices, etc.

10.— (1) The parties to a construction contract may agree on the manner by which notices under this Act shall be delivered.

(2) If or to the extent that there is no such agreement, a notice may be delivered by post or by any other effective means.

(3) Where under this Act a notice is required to be delivered not later than a specified number of days after a particular date and the last of those days is a day which is a Saturday or Sunday or a public holiday (within the meaning of the Organisation of Working Time Act 1997), the notice shall be taken to be validly delivered if delivered on the next day which is not such a day.

← Code of practice for adjudication. Construction Contracts Act 2013 Expenses. →