**Art. 24 RLE Anwendungsreglement zum Baugesetz (RLE)**
RLE
Art. 24 RLE
1 Die Baubewilligung kann nach Mahnung widerrufen werden, wenn die Arbeiten nicht in der üblichen Art und Frist fortgesetzt werden; die Behörde verlangt in diesem Fall die Wiederherstellung eines rechtmässigen Zustandes und ordnet gegebenenfalls die Wiederherstellung des Grundstücks an. [37]
2 Der Gemeinderat informiert das Departement über Verletzungen des Gesetzes über die Ausübung des Bauunternehmerberufs.
[37] Abs. geändert durch R 13.11.1996; in Kraft seit 1.1.1997 - BU 1996, 377.
Gerichtsentscheide zu dieser Bestimmung (6)
52.2017.458 · ti (art. 24 RLE)
Administrative Court Overturns Revocation of Building Permit Due to Premature Action
This provision was the legal basis for the municipal resolution to revoke the building permit due to non-continuation of work, and its potential violation was the core issue leading to the appeal's success.
52.2008.110 · ti (art. 24 RLE)
Appeal Regarding Building Permit Denial for Reconstruction Under Current Zoning Regulations
Cited in relation to the possibility of revoking a building permit if work is not continued appropriately.
52.1998.118 · ti (art. 24 cpv. 1 RLE)
Developer v. Municipality over Lapsed Building Permits and Site Removal
Although the appeal was accepted and the order annulled, the reasoning section discussed the proper application/inapplicability of this article as the basis for the original municipal order.
52.1995.572 · ti (art. 24 RLE)
Property Owner v. Municipality over Unauthorized Construction and Reviewing Authority's Substitution of Judgment
This provision, concerning the revocation of a permit due to lack of work progress, is referenced as the basis for the actions the municipality may take subsequently.
52.2008.110 · ti (art. 24 RLE)
Cantonal Court Upholds Refusal for Rustic Building Reconstruction Post-Landslide
Cited in the reasoning regarding the revocation of a building permit if work is not continued.
52.2017.458 · ti (art. 24 RLE)
Owner v. Municipality on Building Permit Revocation Timing
The decision to revoke the building permit (revocation) was judged premature and thus contrary to law based on this provision concerning permit revocation if works are not pursued in the usual manner and timelines.