Building fine upheld for unauthorized concrete slab work without permit under Building Act.
Legislator-Zusammenfassung
KI-generiertThe Administrative Court of Sweden upheld a building fine against a property owner for pouring a concrete slab with utility pipes without a permit. The owner argued that an interim final notice regarding a single-family house rendered the initial fine unnecessary, but the court found this did not negate the violation. Consequently, the court ruled that the fine remained valid despite the subsequent procedural steps on the house permit.
Legislator-Regeste
KI-generiert10 kap. 3 § PBL; 10 kap. 4 § PBL; Where a building act violation occurs without a permit, a fine may be imposed even if an interim final notice is subsequently issued regarding a related permit application.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVerwandte Entscheide
KI-generiertVolltext
MÖD har fastställt en byggsanktionsavgift för en fastighetsägare som utan startbesked bedömts ha påbörjat en lov- eller anmälningspliktig åtgärd på det sätt som avses i 10 kap. 3 § PBL genom att gjuta en betongplatta med rörledningar. Ett rättelseföreläggande har inte fastställts då nämnden efter sitt beslut om rättelse har meddelat ett interimistiskt slutbesked avseende ett enbostadshus på fastigheten.