Court dismisses appeal for delay in environmental permit review due to unnecessary water authority scheduling request.

Geschäftsnummer ÖM 2011-26
Gericht / Behörde
Rechtsordnung Schweden (SE)
Entscheiddatum
Ausgang Abgewiesen (Dismissed)

Legislator-Zusammenfassung

KI-generiert

The Mark- och miljööverdomstolen dismissed the applicant's appeal regarding delays in an environmental permit application. The applicant argued that the authority unnecessarily requested a time plan from the water authority regarding environmental quality standards review. The court found this procedural step was not an unreasonable delay warranting the appeal's success.

Legislator-Regeste

KI-generiert

49 kap. 7 § RB; The court holds that requesting a time plan from a water authority for environmental quality standard review does not constitute an unreasonable delay under the Administrative Procedure Act.

Schlagwörter

KI-generiert
unreasonable delay environmental permit procedural delay water authority administrative procedure Wasserqualität Planungsverfahren Planungspflicht

Zitierte Gesetzesbestimmungen

KI-generiert
49 kap. 7 § RB
Tillämpning av 49 kap. 7 § RB i ett mål om ansökan om tillstånd enligt 11 kap.
KI-generiert

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

Tillämpning av 49 kap. 7 § RB i ett mål om ansökan om tillstånd enligt 11 kap. MB. MÖD har ansett att MMD försenat målets handläggning i onödan genom att begära en tidsplan från vattenmyndigheten avseende dess översyn av miljökvalitetsnormerna i området.