Contract abandonment by contractor constitutes partial and definitive breach under Civil Code articles 1221-1223.

Geschäftsnummer 0251766
Gericht / Behörde
Rechtsordnung Portugal (PT)
Entscheiddatum
Ausgang Gutgeheissen (Allowed)

Legislator-Zusammenfassung

KI-generiert

The Tribunal da Relação do Porto confirmed the lower court's judgment regarding a construction contract dispute. The plaintiff argued that the contractor's total abandonment of the work constituted a definitive breach of contract. The court held that such abandonment legally qualifies as a partial and definitive incumprimento under the Civil Code, validating the claim for damages.

Legislator-Regeste

Amtlich

EMPREITADA INCUMPRIMENTO DEFINITIVO ABANDONO DA OBRA

Schlagwörter

KI-generiert
contract abandonment definitive breach construction contract partial incumprimento damages for breach

Zitierte Gesetzesbestimmungen

KI-generiert
CCIV66 Art. 1221
CCIV66 Art. 1222
CCIV66 Art. 1223

Zitierte Rechtsprechung

KI-generiert
AC STJ DE 1976/11/11 IN BMJ N261 PAG143

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

[Nº CONVENCIONAL] JTRP00035021

[Nº DO DOCUMENTO] RP200301060251766

[PRIVACIDADE] 1

[TEXTO INTEGRAL] N

[TRIBUNAL RECORRIDO] 2 V CIV PORTO

[URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/97C9082A4037B0FD80256CCC0034BC91?OpenDocument

SUMÁRIO

Face à existência de um contrato de empreitada, o abandono da obra por parte do empreiteiro configura um incumprimento parcial e definitivo.