Court holds contractor's breach of duty of collaboration constitutes debtor's delay in accepting performance under Civil Code.
Legislator-Zusammenfassung
KI-generiertThe Tribunal da Relação do Porto revoked the lower court's decision regarding a contractor's claim for delay. The court found that the owner's failure to collaborate constituted a duty of creditor rather than a true obligation, triggering 'mora accipiendi'. Consequently, the contractor was deemed to have accepted the work late due to the owner's inaction.
Legislator-Regeste
AmtlichCONTRATO DE EMPREITADA VIOLAÇÃO DEVER DE COLABORAÇÃO DAS PARTES MORA DO CREDOR
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVolltext
[DATA DEC. RECORRIDA] 10/13/1998 [Nº CONVENCIONAL] JTRP00025986 [Nº DO DOCUMENTO] RP199906299920419 [PRIVACIDADE] 1 [PROCESSO NO TRIBUNAL RECORRIDO] 207/96-1 [TEXTO INTEGRAL] N [TRIBUNAL RECORRIDO] T J FELGUEIRAS 1J [URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/8C32FCBDBB66071B8025686B00673429?OpenDocument
SUMÁRIO
I - No contrato de empreitada, o dever de colaboração que impende sobre o dono da obra, não constitui uma verdadeira obrigação, mas antes um dever de credor, cuja violação faz incorrer o comitente em
" mora accipiendi ".