Contractor's delay fixed by court only after owner requests it, not unilaterally by owner.

Geschäftsnummer 9720342
Gericht / Behörde
Rechtsordnung Portugal (PT)
Entscheiddatum
Ausgang Abgewiesen (Dismissed)

Legislator-Zusammenfassung

KI-generiert

The court confirmed the lower court's decision dismissing the contractor's appeal regarding a fixed deadline for contract performance. The owner attempted to unilaterally set a deadline without prior judicial intervention, while the contractor argued for procedural fairness. The court ruled that in the absence of an agreed term, the owner must first request the tribunal to fix the deadline before imposing one.

Legislator-Regeste

Amtlich

EMPREITADA CUMPRIMENTO DO CONTRATO PRAZO FIXAÇÃO DE PRAZO TRIBUNAL OBJECTO NEGOCIAL

Schlagwörter

KI-generiert
construction contract performance unilateral deadline fixation judicial time setting contractual delay remedies employer contractor dispute

Zitierte Gesetzesbestimmungen

KI-generiert
CCIV Art. 777, n.º 1, 2
CCIV Art. 400
CCIV Art. 804, n.º 1
CCIV Art. 805, n.º 1
CCIV Art. 808
CCIV Art. 1155
CCIV Art. 1207
CPC Art. 1456
CPC Art. 1457

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

[DATA DEC. RECORRIDA] 11/09/1996

[Nº CONVENCIONAL] JTRP00024439

[Nº DO DOCUMENTO] RP199811099720342

[PRIVACIDADE] 1

[PROCESSO NO TRIBUNAL RECORRIDO] 443/95

[TEXTO INTEGRAL] N

[TRIBUNAL RECORRIDO] T J GUIMARÃES 1J

[URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/586D2E75B52B822D8025686B00671ED0?OpenDocument

SUMÁRIO

I - Em contrato de empreitada no qual as partes não acordaram no prazo de realização da obra, não pode o dono da coisa fixar ao empreiteiro um determinado prazo para o cumprimento, antes deve requerer ao tribunal a fixação de um prazo para tal.

II - Em todo o caso, a fixação de prazo para o cumprimento está dependente da prévia determinação do exacto conteúdo da prestação do empreiteiro.