Agreement on liquidated damages bars creditor from claiming excess damages unless parties agree otherwise.

Geschäftsnummer 0010682
Gericht / Behörde
Rechtsordnung Portugal (PT)
Entscheiddatum
Ausgang Abgewiesen (Dismissed)

Legislator-Zusammenfassung

KI-generiert

The Tribunal da Relação de Lisboa dismissed the appeal, upholding the lower court's decision to fix the parties on a liquidated damages clause. The creditor sought additional compensation for damages exceeding the agreed sum, arguing that the clause did not preclude further claims. The court ruled that by agreeing to a specific penalty amount, the parties implicitly waived the right to claim damages beyond that figure, unless a contrary agreement exists.

Legislator-Regeste

Amtlich

PRESTAÇÃO DE SERVIÇOS CLÁUSULA PENAL

Schlagwörter

KI-generiert
liquidated damages clause excess damages waiver delay in performance contractual penalty party autonomy agreement

Zitierte Gesetzesbestimmungen

KI-generiert
CCIV Art. 810 n.º 1
CCIV Art. 811 n.º 2

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

[Nº CONVENCIONAL] JTRL00007207

[Nº DO DOCUMENTO] RL199609260010682

[PRIVACIDADE] 1

[TEXTO INTEGRAL] N

[URL] https://www.dgsi.pt/jtrl.nsf/33182fc732316039802565fa00497eec/D263293A3F5B3DA08025680300047D17?OpenDocument

SUMÁRIO

Fixando as partes, por acordo, em cláusula penal, o montante da indemnização exigível por atraso no cumprimento, não pode o credor exigir indemnização pelo dano excedente àquele montante, salvo se outra for a convenção das partes.