The Tribunal da Relação de Lisboa dismissed the appeal regarding the quantification of expropriation compensation updates. The court held that the final judgment must explicitly calculate the total updated amount to ensure the indemnity is just. Consequently, the failure to quantify the update in the final decision rendered the provision inadmissible.

Legislator-Regeste

Amtlich

EXPROPRIAÇÃO POR UTILIDADE PÚBLICA INDEMNIZAÇÃO ACTUALIZAÇÃO

Schlagwörter

KI-generiert
expropriation compensation utility public update just indemnity requirement final judgment quantification CEXP91 Article 23

Zitierte Gesetzesbestimmungen

KI-generiert
Art. 23º, nº 1 do Código das Expropriações de 1991

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

[Nº CONVENCIONAL] JTRL00028139

[Nº DO DOCUMENTO] RL200009260039301

[PRIVACIDADE] 1

[TEXTO INTEGRAL] N

[URL] https://www.dgsi.pt/jtrl.nsf/33182fc732316039802565fa00497eec/B6FD55D1AA3E005F80256BAB003B5E3B?OpenDocument

SUMÁRIO

Do disposto no artigo 23º , nº 1, do Código das Expropriações de 1991, resulta que na sentença final deve ser quantificado o montante da actualização da indemnização fixada, por forma a que esta seja, no total, isto é, adiada, do montante da actualização, contemporânea à data da decisão, só assim sendo a indemnização justa.