Contract breach clause nullity extends to entire agreement including performance and delay terms.

Geschäftsnummer 0066886
Gericht / Behörde
Rechtsordnung Portugal (PT)
Entscheiddatum
Ausgang Teilweise gutgeheissen (Partially Allowed)

Legislator-Zusammenfassung

KI-generiert

The court partially allowed the appeal regarding the nullity of contract clauses. The appellant argued that essential clauses related to the promise of performance were void, while the opposing party contended this should not invalidate the entire agreement. The court ruled that if essential clauses concerning the promise of performance are null, the nullity extends to all related clauses, including those on breach and delay.

Legislator-Regeste

Amtlich

NULIDADE DO CONTRATO INCUMPRIMENTO

Schlagwörter

KI-generiert
contract nullity essential clauses promise of performance breach of contract delay clauses contractual integration partial nullity

Zitierte Gesetzesbestimmungen

KI-generiert
CCIV Art. 268(1)
CCIV Art. 364(1)
CCIV Art. 406(1)
CCIV Art. 410(2)
CCIV Art. 762(1)

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

[Nº CONVENCIONAL] JTRL00014835

[Nº DO DOCUMENTO] RL199405050066886

[PRIVACIDADE] 1

[PROCESSO NO TRIBUNAL RECURSO] 8158/913

[TEXTO INTEGRAL] N

[TRIBUNAL RECURSO] T CIV LISBOA 8J

[URL] https://www.dgsi.pt/jtrl.nsf/33182fc732316039802565fa00497eec/ABC3D78FC9D337D680256803000250EF?OpenDocument

SUMÁRIO

- Ocorrendo nulidade do contrato quanto às claúsulas essenciais - mais directamente relacionadas com a celebração do contrato prometido, em cumprimento do contrato-promessa, tal nulidade abrangerá também a parte do contrato respeitante às demais claúsulas relacionadas com o incumprimento, seja ele definitivo ou na espécie de mora.