KI-generiertThe court declared the contract's early termination invalid because an automatic six-month renewal was already in effect at the time of notice. The plaintiff argued for damages based on the breach, while the defendant contended the notice was timely despite the renewal clause. The court ruled that the statutory provisions on contract duration and damages encompass both emergent loss and lost profits, thereby supporting the claim for full compensation.
Legislator-Regeste
AmtlichCONTRATO DE PRESTAÇÃO DE SERVIÇOS RENOVAÇÃO DENÚNCIA PRAZO RESPONSABILIDADE CIVIL DANO EMERGENTE LUCRO CESSANTE
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertZitierte Rechtsprechung
KI-generiertVolltext
[Nº CONVENCIONAL] JTRL00013311 [Nº DO DOCUMENTO] RL199312070054971 [PRIVACIDADE] 1 [PROCESSO NO TRIBUNAL RECURSO] 601/90-2 [TEXTO INTEGRAL] N [TRIBUNAL RECURSO] T CIV LISBOA 6J [URL] https://www.dgsi.pt/jtrl.nsf/33182fc732316039802565fa00497eec/979BD159B1CF3CC080256803000204A7?OpenDocument
SUMÁRIO
I - Estipulando-se no contrato que o mesmo duraria por um periodo de 6 meses, sendo renovável automaticamente por iguais periodos, salvo rescisão com antecedência mínima de 10 dias antes do termo do contrato, tendo a carta de rescisão sido remetida a 29 de Junho e o contrato com início em 1 de Janeiro, então a rescisão
é inválida por já estar renovado o contrato. II - O art. 564-1, CC, abranje não só o dano emergente como os lucros cessantes.