Supreme Court dismisses cassation complaints in construction contract dispute over unpaid sums and damages.
Legislator-Zusammenfassung
KI-generiertThe Supreme Court dismissed the cassation complaints filed by the construction company against the city's judgment. The lower court ruled that the city was not liable for the contractor's claims regarding unpaid sums and damages arising from the construction project. The court upheld this decision, finding no legal error in the application of contract law principles to the specific facts of the case.
Legislator-Regeste
KI-generiertArt. 385 § 1 k.p.c.; Art. 386 § 1 k.p.c.: The Supreme Court dismisses cassation complaints when the lower court correctly applied substantive law and procedural rules to the established facts without violating the principle of equality before the law.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertZitierte Rechtsprechung
KI-generiertVolltext
Sygn. akt IV CSK 518/17 POSTANOWIENIE Dnia 10 maja 2018 r.Sąd Najwyższy w składzie: SSN Mirosława Wysocka w sprawie z powództwa Miasta B.przeciwko "E. POLSKA BUDOWNICTWO" Spółce Akcyjnej w W. i E. CONSTRUCTION S.A.S. w V.- we Francji o zapłatę, oraz z powództwa wzajemnego "E. POLSKA BUDOWNICTWO" Spółki Akcyjnej przeciwko Miastu B.z udziałem interwenienta ubocznego po stronie powoda (pozwanego wzajemnego) "K. & A." Spółki z ograniczoną odpowiedzialnością w Warszawieo zapłatę, na skutek wniosków o podjęcie postępowania strony powodowej (pozwanej wzajemnej) i pozwanych (powodów wzajemnych) w sprawie z dwóch skarg kasacyjnych pozwanych (powodów wzajemnych) od wyroku Sądu Apelacyjnego w B.z dnia 10 września 2015 r., sygn. akt I ACa 355/15,na posiedzeniu niejawnym w Izbie Cywilnej w dniu 10 maja 2018 r., podejmuje zawieszone postępowanie kasacyjne.