ECLI:NL:RBZWB:2025:553
ECLI:NL:RBZWB:2025:553
KI-generiert
Gas and electricity supplier wins against tenant who denied living at address but admitted using their contact details.
Legislator-Zusammenfassung
KI-generiertThe court ordered the defendant to pay outstanding gas and electricity bills totaling €2,219.51 plus interest and legal costs. Although the defendant denied living at the address, they admitted using their personal contact details and confirmed a contract existed, while also acknowledging early termination. The court found the evidence sufficient to establish the contractual relationship and liability for the termination fee.
Legislator-Regeste
KI-generiertArticles 6:96 and 6:119 of the Civil Code; A supplier may claim payment for services rendered when the consumer's conduct (such as using their contact details) objectively indicates acceptance of the contract, even if they later deny residence.
Schlagwörter
KI-generiert
utility supply contract
early termination fee
consumer acceptance
civil court judgment
payment order
Energielieferungsvertrag
Forderungsklage
bestrittene Forderung
Zitierte Gesetzesbestimmungen
KI-generiertArticle 6:96 paragraph 6 of the Civil Code
Article 6:119 of the Civil Code
Directive on Reasonable Termination Fees of the ACM
artikel 6:96 lid 6 BW
artikel 6:119 BW
Zitierte Rechtsprechung
KI-generiertVerwandte Entscheide
KI-generiertECLI:NL:RBAMS:2022:745
Court dismisses utility company's claim for unpaid bills due to lack of proven contract formation and failure to meet consumer information duties.
ECLI:NL:RBNHO:2022:1962
Consumer wins distance contract dispute; court extends withdrawal period due to missing info, barring termination fee.
ECLI:NL:RBNHO:2024:12619
Court dismisses gas supplier's claim due to unfair trading practices and orders contract annulment.
ECLI:NL:RBAMS:2022:605
Court voids gas contract due to missing written form requirement and orders defendant to repay disputed amounts.
ECLI:NL:RBROT:2025:4428
Court orders former partners to pay unpaid electricity bill, collection costs, and interest to Engie.