ECLI:NL:GHSHE:2020:2024
ECLI:NL:GHSHE:2020:2024
KI-generiert
Court partially allowed appeal against final judgment, upholding interim decision in construction contract dispute.
Legislator-Zusammenfassung
KI-generiertThe Court of Appeal upheld the interim judgment of January 2015 but partially revoked the final judgment of May 2017 regarding the contractor's claim. The appellant successfully argued that the contractor failed to prove full performance of the construction work, while the court found no merit in the interim proceedings. Consequently, the final judgment was set aside in part, ordering the contractor to pay the contractor's claimed amount plus interest and legal costs.
Legislator-Regeste
KI-generiertUAV 1989; BW 6:119: Where a contractor fails to prove full performance of work under a construction contract governed by the Uniform Administrative Conditions, the court may partially revoke a final judgment to order payment of the proven portion plus interest.
Schlagwörter
KI-generiert
construction contract dispute
interim judgment upheld
final judgment revoked
Uniform Administrative Conditions
payment of proven portion
legal costs allocation
Burgerlijk Wetboek
Zitierte Gesetzesbestimmungen
KI-generiertUAV 1989
BW 6:119
artikel 2 lid 1 UAV
artikel 2 lid 3 UAV
artikel 7 lid 1 UAV
artikel 1 lid 2 UAV
artikel 6:248 lid 1 BW
artikel 6:248 lid 2 BW
Artikel 7:755 BW
artikel 6:145 BW