Legislator Rechtsprechung & Gesetzgebung
IEHC 248 ECLI:IE:HC:2015:248 KI-generiert

High Court quashes planning consent for wind turbines due to missing cumulative environmental impact assessment and remits case.

Geschäftsnummer IEHC 248
Gericht / Behörde
Rechtsordnung Irland (IE)
Entscheiddatum
Ausgang Teilweise gutgeheissen (Partially Allowed)

Legislator-Zusammenfassung

KI-generiert

The High Court quashed the planning consent for wind turbines because the Environmental Impact Statement failed to assess cumulative effects with the national grid connection. While the developer argued remittal was impossible without a new study, the Board contended it could conduct a fresh assessment. The court decided to remit the matter to the Board, balancing the need for a proper environmental review against the potential waste of time and cost for the developer.

Legislator-Regeste

KI-generiert

Section 50 and Schedule of Articles of the Planning and Development Act, 2000; The court must quash a planning decision where cumulative environmental effects were not assessed and remit the matter to the planning authority if it is satisfied that a fresh assessment can be conducted to comply with the judgment.

Schlagwörter

KI-generiert
cumulative environmental effects Environmental Impact Statement planning consent quashed remittal to planning authority wind turbine development national grid connection procedural fairness

Zitierte Gesetzesbestimmungen

KI-generiert
Section 50 of the Planning and Development Act, 2000
IN THE MATTER OF AN APPLICATION UNDER SECTION 50 AND SOA OF THE PLANNING AND DEVELOPMENT ACT, 2000 (AS
Schedule of Articles of the Planning and Development Act, 2000

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

Neutral Citation: [2015] IEHC 248

THE HIGH COURT

JUDICIAL REVIEW

Record Number: 2014 No.19 JR

IN THE MATTER OF AN APPLICATION UNDER SECTION 50 AND SOA OF THE PLANNING AND DEVELOPMENT ACT, 2000 (AS

AMENDED)

BETWEEN:

POL O GRIANNA, GERALDINE UI DHUINNIN, AOIFE NI DHUINNIN, CLIODHNA NI DHUINNIN, BERNADETTE COTTER, TIM

O'CONNELL, CAOIMHGHIN O BUACHALLA, PADRAIG D. KELLEHER, ALAN KING, XAKAROO

APPLICANTS

AND

AN BORD PLEANALA

RESPONDENT

AND

CORK COUNTY COUNCIL

FIRST NAMED NOTICE PARTY

AND

FRAMORE LIMITED

SECOND NAMED NOTICE PARTY

Decision of Mr Justice Michael Peart given on Remittal Application: 16th April 2015:

1. In this case the Court has determined that the construction of the wind turbines themselves and the connection to the national

grid is a single project, and not two separate projects, and that before granting planning consent for the former, it was necessary

that the cumulative effects of the combined or single project ought to have been carried out. In circumstances where that has not

happened, I concluded that the decision should be quashed. I will come to the terms in which that order should be made.

2. Having determined that the decision should be quashed, the question of whether the matter should be remitted to the Board has

arisen. The Board has submitted that it is an appropriate case for the Court, in the exercise of its discretion, to remit the matter so

that it can carry out an EIA in a way that reflects the findings and conclusions of this Court in its judgment. That application is

opposed by the applicants, but is supported by the Second Notice Party, Framore Limited.

3. The reason why the EIA did not include an assessment of the cumulative effects of stage two of the development, namely the

connection to the national grid, is that the EIA submitted by the developer as part of its application for planning consent did not

include a statement of the environmental effects associated with the second stage. The reason for that was submitted to have been

beyond its control since it was a matter for ESB Networks to specify the route and specifications in that regard.

4. However, the Board is satisfied that if the matter is now remitted to the Board, an EIA can be carried out by the Board which will

meet the requirements for a cumulative assessment in line with the findings of this Court, and that it is unnecessary for the entire

process to be recommenced before the planning authority.

5. The Board has stated also that in so far as the EIS already submitted did not contain the necessary information for an EIA in

respect of the works necessary for a connection to the national grid, the Board upon remittal can exercise its power under the

Regulations to request a further EIS in that regard, and that in that event a notice will have to be published which will give the

appropriate notice and opportunity for submissions to any interested third party who may wish to object.

6. The Board has submitted, as has Framore, that it would be wasteful both in terns of cost and time if the matter was not simply

remitted for a further EIA to be carried out in the light of the Court's conclusions, and particularly as in this case where so many of

the grounds of objection made by the applicants in these proceedings were rejected by the Court.

7. The applicants on the other hand submit that the illegality which was found by the Court to exist in the decision cannot be cured

by remittal to the Board. They submit that what is required now for the Court's findings to be complied with is an entirely new EIA

which addresses the cumulative effects on the environment of both stages of this proposed development, and that the EIS as lodged

already cannot now simply be revisited by the Board so that a fresh assessment can be carried out by reference to that EIS in order

to comply with the Court's decision- the reason being that the EIS does not address for the reasons stated the likely effects of the

works necessary for a connection to the national grid.

8. It is submitted that in circumstances where clearly a new EIS must be prepared and submitted which takes account of the

cumulative effects of both stages of the development, a remittal is inappropriate. The applicants do not agree that the powers

available to the Board under the PDA 2000 and the Regulations enable the Board to comply with the requirements for an EIA in

accordance with the Court's judgment.

9. This Court must regard the Board as a disinterested party. It has no stake in the commercial venture being pursued by Framore. If

the Board as a statutory body charged with making decisions in these matters has taken the view that in the light of the findings of

this Court it can carry out an EIA which accords with the Court's findings if the matter is remitted to it for a fresh decision, this Court

should not lightly reject such an application to remit in favour of simply quashing the decision simpliciter with the result that the

application goes back to square one. That has the potential to be wasteful in terns of delay and cost, and this Court ought not to

adopt a course which is unnecessarily onerous upon the developer. There could be no question of this Court penalising the developer

for not having proceeded correctly in the first instance, or because the decision made by the Board has turned out to be flawed

because the EIA, based upon the EIS submitted by the developer, has been found to be flawed for all the reasons which have been

given.

10. The Court should decide whether or not to remit on the basis of fairness and justice. If the situation can be reasonably expected

to be remedied if remitted, and particularly where the Board is of opinion that this is the case, then this Court ought to remit the

matter. That does not mean that this Court has in advance given some sort of 'imprimatur' to whatever new EIA is carried out for the

purpose of any new decision the Board may make. If the applicants are not satisfied that the new EIA has been carried out in

accordance with law, no doubt they will be entitled to again seek leave to challenge it, as they did before. For that very reason, it

stands to reason that this Court should take very seriously a submission by the Board itself that it will be in a position to carry out a

fresh EIA in the light of the Court's judgment. If the Board was not of that view, it would make no sense for it to seek such a remittal,

even if the developer was keen to take a chance that it would achieve the desired result from its point of view.

11. In all the circumstances, I am satisfied that the justice of the case requires that the decision be remitted to the Board.