IESC 51 ECLI:IE:SC:2014:51 KI-generiert

Contract award review precludes entity from concluding contract automatically upon application filing under EU Regulations.

Geschäftsnummer IESC 51
Gericht / Behörde
Rechtsordnung Irland (IE)
Entscheiddatum
Ausgang Abgewiesen (Dismissed)

Legislator-Zusammenfassung

KI-generiert

The Court ruled that a contracting entity is automatically barred from concluding a contract once a review application is filed under Article 8(1)(b) of the EU Regulations, regardless of the standstill period's expiration. The appellant argued for judicial discretion to allow contract completion before the review's final determination, but the Court found no such jurisdiction in the Regulations. Consequently, the appeal was dismissed because the statutory framework mandates an automatic preclusion without requiring a separate motion.

Legislator-Regeste

KI-generiert

Article 8(1)(b) of the European Communities (Award of Contracts by Utility Undertakings) (Review Procedures) Regulations, 2010; Article 8(2) of the same Regulations: The filing of a review application automatically precludes the contracting entity from concluding the contract, rendering any request for judicial permission to proceed inadmissible.

Schlagwörter

KI-generiert
contract award review automatic preclusion standstill period utility undertakings judicial discretion EU Regulations tenderer rights

Zitierte Gesetzesbestimmungen

KI-generiert
Article 8(1)(b) of the European Communities (Award of Contracts by Utility Undertakings) (Review Procedures) Regulations, 2010
is precluded from concluding the contract in question under the provisions of Art. 8(2) of the Regulation notwithstanding
Article 8(2) of the European Communities (Award of Contracts by Utility Undertakings) (Review Procedures) Regulations, 2010
is precluded from concluding the contract in question under the provisions of Art. 8(2) of the Regulation notwithstanding

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

THE SUPREME COURT

[Appeal No: 274/14]

Clarke J.

Laffoy J.

Dunne J.

Between/

OCS One Complete Solutions Limited

Applicant/Respondent

and

Dublin Airport Authority plc

Respondent/Appellant

and

Maybin Support Services (Ireland) Limited t/a Momentum Support

Notice Party

Ruling of the Court delivered on the 31st July, 2014 by Mr. Justice Clarke

1. The Court, having considered the written and oral submissions of the parties, is in a position to indicate its principal conclusions on

the issues which arise on this appeal. A full judgment outlining the reasoning of the Court will be delivered in due course.

2. However, the Court has concluded that:-

(a) Once an application is made to the Court under the provisions of Article 8(1)(b) of the European Communities (Award

of Contracts by Utility Undertakings) (Review Procedures) Regulations, 2010 ("the Regulations") seeking the review of a

decision of a contracting entity to award a contract to a particular tenderer or candidate, the relevant contracting entity

is precluded from concluding the contract in question under the provisions of Art. 8(2) of the Regulation notwithstanding

the fact that the relevant application to the Court is initiated after the standstill period provided for in the Regulation has

expired. Furthermore, it is unnecessary for the applicant to make a specific application by motion to the Court in order

that such a preclusion come into effect. Rather the preclusion arises automatically on the bringing of the substantive

application under Art.8(1)(b).

(b) The Regulation does not confer on the courts a jurisdiction to entertain an application by the contracting entity

concerned to be permitted to conclude the relevant contract prior to the determination of the application for review;

(c) In those circumstances the question of the criteria which would apply on such an application, were one permitted to

be made, does not arise; and

(d) It is also unnecessary and inappropriate to determine the issues which were debated on this appeal concerning the

merits of the outcome of such an application on the facts of this case.

3. In those circumstances the appeal will, when the Court has an opportunity to deliver its full judgment, be dismissed and the notice

to vary allowed.