High Court dismisses plaintiff's conspiracy claim due to lack of prima facie proof of unlawful agreement.
Legislator-Zusammenfassung
KI-generiertThe High Court dismissed the plaintiff's application for a direction at the close of their case regarding a conspiracy claim. The plaintiff alleged defendants conspired to withhold unpaid subcontract money, but the court found no prima facie proof of an unlawful agreement. Consequently, the court awarded costs to the defendants against the plaintiff.
Legislator-Regeste
KI-generiertConspiracy Act 1880; Common Law: A conspiracy claim fails where the facts and circumstances do not establish a probability of an unlawful agreement to deprive another of their due.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVerwandte Entscheide
KI-generiertVolltext
Neutral Citation Number: [2011] IEHC 490
High Court
Commercial
2010 10074 P
Between
Mero-Schmidlin (UK) PLC
Plaintiff
and
Michael McNamara and Company, Cedartree Construction Limited, Bruce Shaw Project Management Limited, Bernard
McNamara, John Balance, Paul Hanby, Paul Newman and John McGowan
Defendants
Judgment of Mr Justice Charleton delivered on the 13th day of December 2011
This is an application for a direction at the close of the plaintiff's case. It arises out of a large building project called ‘McDonagh
Junction’ in Kilkenny where the second named defendant Cedartree Construction Ltd was the employer, the first named defendant
Michael McNamara and Company was the main contractor, the third named defendant Bruce Shaw Project Management Limited was
the project manager and the plaintiff was the subcontractor for a glass roof. The other defendants were employees of the first three
named defendants. I will refer to that later.
The plaintiff alleges that the defendants conspired to keep it out of money due to it, approximately the unpaid half of the subcontract
price in order to smooth future business relations or, in the alternative, to keep moneys due to the plaintiff for themselves.
Where the defendants on this kind of application indicate that they will go into evidence should the application be unsuccessful, the
court should only grant a direction where there is no prima facie proof; where the defendants indicate that they will not give
evidence, the task of the court is to analyse such evidence as has been given by the plaintiff in order to determine if proof amounting
to a probability has been established. The court has a discretion to hear the defence case, should it be announced that there is to be
one, before deciding on such an application. All of the defendants have stated that they will go into evidence should this application
not be granted, so I bear this discretion in mind.
The entirety of the case made by the plaintiff has been based upon circumstantial evidence. I do not intend to repeat the analysis
that I have made elsewhere as to the proper approach by a court trying a civil case based on such evidence. It suffices to say that a
theory that a wrong has been committed against the plaintive is not enough; rather, the facts and circumstances upon which the
case of conspiracy is made out must establish it as a probability; which probability will be destroyed in the event that on the same
facts and circumstances some other equally probable explanation is available. This principle derives from the criminal law principle that
a jury should not convict on circumstantial evidence unless that evidence establishes by undesigned coincidence and beyond a
reasonable doubt that the accused is guilty and that no other reasonable hypothesis will fit the same circumstances. Where proof by
probability is in issue, there may seem to be a logical trap in first deciding that the facts and circumstances prove a probability but
then analysing the same material to see if anything else may be probable thereupon. That, however, is not so. The proper approach is
to analyse the material in order to establish if a probability is established and then to return and re-analyse the material in order to
attempt to find, as a safeguard, any other conclusion which might amount to a competing probability, thereby displacing any
tentative finding of fact; see Elliott Construction Ltd v Irish Asphalt Ltd (High Court, unreported, 25 May 2011). Here I am concerned
with whether there is prima facie proof only, that is to say a sufficiency of evidence which if not contradicted would allow a tribunal
of fact to fairly conclude that there was a conspiracy. In that regard, I intend to concentrate on whether there is sufficient prima
facie evidence of that tort.
A civil conspiracy occurs where two or more parties agree to further their interests to the detriment of another party by using
unlawful means. That unlawful means can be the object of the conspiracy or it can be the mechanism whereby something apparently
lawful is accomplished. In each case the essence of conspiracy as a tort is the coming together in a combination to agree on an
illegality. It can also be the tort of conspiracy that a combination wilfully to do an act causing damage to a man in his trade or other
interests is unlawful and if damage in fact is caused is actionable, unless the real and dominant purpose is to advance the lawful
interests of the parties to that agreement in a manner in which they honestly believe that those interests would directly suffer if the
action were not taken; see Heuston – Salmond on Torts (17th edition, 1977, para 138). It is the first kind of conspiracy which is
relevant here. An agreement by an individual with his company can be a conspiracy as can an agreement between companies through
individuals and an agreement between individuals and companies; Taylor v Smyth [1991] 1 IR 142.
There has been debate as to the nature of the claim taken by the plaintiff against the defendants. The plenary summons alleges
various torts. I am satisfied that the claim before this Court is in conspiracy only. I accept the argument advanced on behalf of the
defendants on this aspect of the application. In the letter of claim before the issue of proceedings, dated 12 October 2010, the
solicitors for the plaintiff make explicit an allegation that an agreement by way of conspiracy was reached on about 1 July 2008
whereby it was agreed between the defendants, or on their behalf, that a full and final settlement of building debts between the
parties to that agreement would be reached to include monies due to the plaintiff but, according to the letter, the monies due to the
plaintiff would not be pursued. In evidence, Mr David Barrow on behalf of the plaintiff put forward his interpretation of the conspiracy,
which was that on that date the parties agreed to the payment of the money that was due to the plaintiff but were determined that
the plaintiff would never receive it because they would keep it for themselves, or one or other of them. His evidence was focused on
conspiracy and that was what he was cross examined about. There were references to interference with contractual relations and
breaches of duty. In the pleadings, the claim of conspiracy is squarely made as part of other pleas made of interference with
contractual relations and of breach of duty. The alleged agreement is central to the allegation of interference with contractual
relations made against the defendants; that is how the matter is pleaded, and properly so. Any such interference, if it occurred,
happened not as an individual wrong but instead it is pleaded as part of the conspiracy of the defendants, as the means whereby the
alleged conspiracy to use unlawful means, through interference with contractual relations and breach of duty, was furthered. No
criticism of the pleadings is advanced in that regard. It is clear from the initial letter that the wrong suffered by the client is reflected
in the allegation of conspiracy as opposed to any other claim. The wrongs alleged in addition are the means whereby the agreed
unlawful actions in furtherance of the conspiracy have been claimed to be taken.
In addition, it has been argued on behalf of the plaintiff that beyond conspiracy there is a claim of negligence based on breach of
duty. The extensive contract documents establish that there is no privity between the plaintiff and any other party than the first
defendant; the relationship is that of subcontractor to main contractor. Clause 11 (F) of the subcontract between the plaintiff and
the second named defendant allow the plaintiff to stand in the shoes of the first defendant as main contractor and to bring an action
against the second defendant, as employer on the building works, in the same manner as if the contract were made with it. This
provision is enabled where the plaintiff is dissatisfied with non-certification or under-certification of work, the task of the third named
defendant. The relations between the parties are thus governed in such a way that the contract provisions and entitlement to
arbitrate clauses preclude a special relationship that otherwise might be argued to give rise to a duty of care; Pacific Associates v
Baxter [1990] 1QB 993. In that case there was in addition to the kind of arrangement of liabilities between co-workers on a building
project a specific clause limiting liability. That, however, is not necessary where the relations between the parties exclude a special
relationship giving rise to liability for breach of a duty of care through those relations being worked out and defined through contract.
In that case at p 1072 Ralph Gibson LJ stated:
The professional firms engaged in construction work as architects or engineers or surveyors, and the companies which
carry out such work, are concerned to know whether in the relationships between contractor, employer and engineer
under a contractual relationship like to that set out in this contract, but ignoring the disclaimer clause, the law imposes a
duty of care on the engineer to the contractor, not to cause economic loss to the contractor in the process of certifying
and of accepting or rejecting claims under the contract. Of course, each case will depend on its own facts and on the
relevant provisions of the contract: see per Lord Morris of Borth-y-Gest in Sutcliffe v Thackrah [1974] AC 727, 752g. but
it is likely that a large number of contracts are placed for construction or engineering works in which the contractual
relationship of contractor and employer and the contractual duties of the engineer are substantially similar to those
present in this case and it should be possible to determine whether in general a duty of care does or does not arise in
such a case…[O]n the facts … there was “no express or implied undertaking of responsibility” (see per Lord Devlin in
Hedley Byrne and Co Ltd v Heller and Partners Ltd [1964] AC 465, 530) on which the alleged liability of the engineer could
be founded…
At p 1037 Russell LJ founded his concurring view on the contractual structure. He said this, with which I agree for the purpose of the
contracts that I have analysed herein:
In my opinion the following question is worthy of being posed. Given the contractual structure between the contractor
and the employer, can it fairly be said that it was ever within the contemplation of the contractor that, outside the
contract, it could pursue a remedy against the engineer? I do not believe that any representative of the contractor would
have thought so for one moment, nor do I believe that from an entirely objective point of view the answer could be
anything other than in the negative. The contractor in reality had its rights adequately protected by the terms of its
bilateral contract with the employer. If the contractor had thought not, then it was at liberty to insist upon a tripartite
contract before embarking on the work.
There have been other sets of proceedings prior to this one, and there is a further set of proceedings waiting. In this proceeding, the
plaintiff has already obtained judgment in May 2011 against the first named defendant for €1.8 million on an undefended claim. Arising
out of the slow sale of building works in 2007-2008, which I describe below, the main building contractor, the first named defendant
was told in late 2008 that the employer, second named defendant, had a deficit problem. The first named defendant obtained
judgment for, using round figures, €1.02 million against the second named defendant in early 2009. That did not include any monies
owed to the plaintiff. On March 2nd of the same year the plaintiff sued the first named defendant for debt due to them as a
subcontractor to it as main contractor and the second named defendant as employer on the building project in respect of work done
for them and monies owed. On March 9th of that year the plaintiff was awarded judgment against the second named defendant
requiring it to certify for works done for it and a declaration that this defendant had been unjustly enriched as a result of work done
by the plaintiff to the tune of about €1.8 million including VAT. The claim of the plaintiff as subcontractor against the first named
defendant as main contractor for debt went to arbitration. This did not turn out in the plaintiff’s favour because the arbitrator held
that though the first named defendant owed the plaintiff money, that such money was owed under a pay if paid contract; until the
first named defendant was paid by the second named defendant for the work of the plaintiff, that defendant had no contractual
liability to pay. This ruling was in March 2010. Then the plaintiff returned to its original proceedings; the declaration it had obtained
against the second named defendant was turned into a money judgment by order of the High Court. That was appealed to the
Supreme Court and overturned. The logic behind the order of the High Court is clear and attractive but is not open to me. I am
confined to a claim in conspiracy. In addition, the third named defendant, as project managers of the development, pursued the
ultimate owner of the development for fees due to them in their work. They obtained a judgment but that was cut down due to a
creditors’ arrangement to just over half. The first named defendant is now in receivership under the National Assets Management
Agency. The second named defendant is pleaded in the statement of claim to be unable to meet any claim made.
These proceedings for conspiracy and other pleaded torts were initially launched against the three corporate defendants, the first,
second and third named, but were later amended to bring in the other five defendants on the basis that the activities of the
corporations were directed by them and that they personally entered into the conspiracy. In so far as I might be found to be
incorrect as to a claim not being made in interference in contractual relations, holding as I do that this claim is pleaded as the means
whereby the conspiracy was agreed to be effected by unlawful means, I would accept as a matter of principle that unless there is an
assumption of personal responsibility on behalf of a director or employee so as to create a special relationship between that person
and a plaintiff, that liability for acts done on behalf of a corporation rests with that entity: Williams v Natural Life [1998] 1 WLR 830.
To that extent, there is no evidence of such an assumption of responsibility. Further, it is difficult, outside the claim of conspiracy
made in this case, to see how individuals who at all times acted for corporate employers and in explicit terms under relevant notice in
that regard through emails and headed notepaper, could ever be made liable for that tort. It is even more difficult to see how the
liability in this case can be, as I have said, governed by anything other than contract relationships. Any breach of those contract
relationships was effected through corporations fairly and explicitly displayed to the parties as the acting parties. I do not at all see a
situation arising such as that which occurred in Shinkwin v Quin-Con Ltd [2001] 1 IR 514. There is no evidence of that kind on which I
could see a prima facie case. It is different, of course, should the parties have entered into a conspiracy with the other defendants,
whether as corporations or as individuals.
It is important to concisely put this into context. The plaintiff company supplies a specialist form of subcontracting in glasswork and
they are very good at that job. Things can, however, go wrong. Typical of the work they do is the job in question here. The job
which the second named defendant had employed the first named defendant to build was a shopping centre and residential
development in Kilkenny, to be called McDonagh Junction. The plaintiff was asked to roof in glass a large courtyard between buildings
in the older part of an existing complex of a once derelict workhouse. I am going to use round figures in this judgment, as they give a
better view of the overall picture. The total cost of the development was around €115 million and the subcontract sum due to the
plaintiff was around €3 million plus VAT. For their work they have been paid about €1.4 million. They claim to be owed about €1.6
million and VAT, which brings it to € 1.8 million. This specialist subcontract work of the plaintiff involved putting up steel trees with
branches supporting a concave structure of glass over an open area between retail buildings. In this ambiance of light and space
people can trade and supply refreshments. Each of the panes of glass was large. While continual sunshine is rare in Ireland, it must
nonetheless be provided for. The panes of glass were in two layers and in between there was a treatment for ultraviolet penetration,
a ‘California layer’, and a dotting pattern that would keep out around half of the light. This job would be outside the normal experience
of even a large building contractor and the plaintiff was therefore the specialist subcontractor of the first named defendant for this
project. A firm of architects, who are not defendants, were initially employed by the second defendant, as developer, to oversee the
work. Normally, a firm of architects would do the certification on a large building project; thereby enabling the contractor and its
subcontractors to be paid. In this project, that task was taken over by the third named defendant. Another firm of a similar name
were the quantity surveyors. In so far as it matters, I do not see any difference between these two firms. I see them as being
identical in these The fifth named defendant worked for the third named defendant. The fourth named defendant was an important
person in the first named defendant as was the eighth named defendant. The sixth and seventh defendants were important people in
the second named defendant.
None of what follows would have happened but for an exchange of ideas between the architects and the plaintiff as to whether it
was possible to have smaller dots within the panes of glass over the courtyard. At the time of this discussion, the architects had
been taken over by the first named defendant as contractor’s architect. In due course what had been a 20 mm dot was changed to a
very much smaller 4 mm dot. The glass was not manufactured by the plaintiff, but by two companies in England called Romag and
Buckleberry. Occluding dots are put onto glass by a photographic type of process. Because of the size of the panes of glass to be
used, photographic film was not large enough to fit over each pane in order to imprint the dots. There was therefore overlap on that
film when two sheets were fitted together in order to treat the entire surface. On that area of overlap, the dots were microscopically
different in size in comparison with the areas where a single film could be used. When the glass was put up over the courtyard, clear
bands of darker shading, running horizontally or vertically, appeared in an obvious fashion. This is an aesthetic problem, but it was
nonetheless a serious issue. As I have said, in round figures, the plaintiff was to be paid €3 million for this job. At the time in the
dispute as to the banding issue broke out, the plaintiff had been paid just shy of half that amount. In August 2007, it became
apparent that the glass was not as the second named defendant or the third named defendant expected. On 27 August of that year
the resident architect rejected the glass. Following that, the plaintiff wrote to Romag requiring them to take back the glass, explicitly
stating that it was defective and that they should just come and pick it up from Kilkenny. It was made plain to the plaintiff that the
glass was not acceptable. Because of the interaction between the architect and the plaintiff in ordering the glass, the case is now
made that the glass condition was not the responsibility of the plaintiff. I cannot accept that. Once the defect became known, the
responsibility for it was that of the plaintiff and the plaintiff alone. There was correspondence lasting over a period of a year, with
four different meetings between the interested parties on 17 October 2007, 9 July 2008, 22 August 2008 and 15 September 2008, in
order to try and resolve the glass issue in terms of either removal or an abatement of the price due to the plaintiff. The evidence for
the plaintiff has been that this correspondence, and these meetings, did not amount to genuine attempts to resolve the differences
between the developer, the main contractor, the representative of the employer and the plaintiff. The plaintiff is painted as without
fault in these negotiations. I need to return to that proposition.
Other factors also need to be brought into the mix. The plaintiff did not pay Romag for the glass, and that account remains
outstanding in a sum of around €300,000. The plaintiff was asked for an alternative design specification but did not respond. The
plaintiff was asked to pick up a glass sample in Kilkenny with the same size dot size but did not choose to do so. During the latter part
of these events, the plaintiff began to be advised by outside parties and came to the conclusion, ultimately, in September 2010 that
a conspiracy was in operation to deprive it of its money or to steal its money. The evidence on behalf of the plaintiff was that the
issue of payment was constantly being put off with excuses being made not to pay and that these activities amounted to dishonesty.
It is said that the court should draw inferences positively against the defendants to support the allegation of conspiracy because
these excuses were so flimsy and transparently unsound. There are, it seems to me, some important factors to be added in here. In
the event that the second named defendant, as developer, instructed the first named defendant as main contractor, to change the
dot size in this glass, under the contract such an instruction would have amounted to a variation. It has been made explicit in
evidence to the court that in such an event the plaintiff would expect to be paid on that basis; and would therefore be due what
would amount to a considerable sum for removing all of the glass and replacing it. These factors make it very difficult for the Court to
come to the conclusion that all of the to-ing and fro-ing complained of amounted to a concerted action in furtherance of a conspiracy
by the defendants as is alleged. Furthermore, the first named defendant at all times submitted the account of the plaintiff to the
second named defendant for payment. In October 2008, the third named defendant and the plaintiff agreed a final account of monies
due to the plaintiff in the sum of €1.6 million, but this was subject to abatement. This is claimed not to have been genuine. In reality,
correspondence immediately thereafter from the fifth named defendant on behalf of the third named defendant to the paying party
sought a sum of money in early course allowing for a discount of €600,000 on the defective glass but clearly and genuinely seeking to
obtain a payment for the plaintiff of around €1 million. Later, in 2009, following the collapse of the unsupported property marked in
Ireland, when a bank became involved, there was nothing apart from prudence which led that bank to require that such defects
issues as remained must be cleared up. An allowance in support terms was made for under €1 million, but that allowance was
nonetheless made and made in circumstances which bear no suggestion of bad faith.
A great deal of time has been spent on the issue as to who was responsible for the defective glass. Whereas this is not determinative
of the issue of conspiracy, it is important that I express a view. In structuring large building projects, it is important that the parties
can reach a clear conclusion as to which party will be responsible should any defect occur. A failure or inadequacy in materials can
arise from improper choice or from improper manufacture or from improper design. Many different specialties may be involved in a large
project and each of these will depend on the other to some extent. A defect can occur notwithstanding a specialist subcontractor
being engaged. Defining responsibility in that event is the task of those who write the contract, or contracts, in order to reflect the
intention of the parties. Some of these parties may lack knowledge as to the properties of steel structures, or bricks, or roofing
material, or tiles or glass. If, for example, a contract is made that a particular material should be durable over a particular period of
years, then the party supplying under that agreement assumes precisely that defined liability. The main contractor in bringing in
specialised subcontractors is entitled to rely on their skill and knowledge and is entitled to proceed to structure the interrelationship
of contracts so that what is supplied by a subcontractor will be the responsibility of that subcontractor alone. An architect, acting on
behalf of an employer or on behalf of a main contractor is entitled to specify a particular material and to rely on the subcontractor to
supply that material; provided that the form of the contract so provides. Here, the relevant subcontract clause which binds the
plaintiff in its relationship with the first named defendant as main contractor, and is ultimately the description of responsibility upon
which the second named defendant, as developer, is entitled to rely and to seek to enforce through the proper use of the contract
provisions with the main contractor, is clause 6.6.4. Under the heading of "surface treatments generally", it is provided that "All
applied coatings (e.g. low emissivity coatings or frittings) shall be uniform in tone, hue, colour, texture, pattern and opacity and shall
provide a consistent appearance to the glazed units. Any noticeable difference between one unit and another will not be permitted,
unless expressly specified."
This clause clearly delineates the reposing of responsibility in the plaintiff for the glass quality. No matter who was responsible
ultimately for the banding appearance in the glass, Buckleberry or Romag or the plaintiff, and no matter who was told what, the
clause is effective in terms of its plain words. It may be likened to a repair clause in a lease. In that instance, the condition of the
building on demise does not matter or how the defect in it arose; what matters is the nature of the responsibility undertaken by the
tenant. In this clause the responsibility undertaken by the plaintiff as subcontractor was to supply a glass for the courtyard roof
which was uniform in appearance. It was not. No issue of real argument in respect of responsibility could arise. This had previously
been defined by the contract. An argument might be made that the defect was not very important: but that argument becomes
untenable in the context of the choice of the plaintiff to provide a product of excellent quality. Thereafter, had the glass not been
rejected, which it was, an argument might be made as to abatement. Were I to try and sort out the contract dispute, which is not
before me, as between the plaintiff and the first named and second named defendants, that latter course might arise under a
contract clause to which I shall shortly refer, it might be remarked that the determination by the plaintiff to avoid the considerable
costs of removing and replacing the glass, to a possible cost of possibly close to the amount the plaintiff was owed, but to seek an
abatement eventually resulted in the agreement of 22 October 2008 with the third named defendant but even this was subject to a
further agreement as to the correct level of abatement. The plaintiff was responsible for the glass defect and it was serious and it
should not have occurred. It was reasonable to require the replacement of the glass.
I now want to put the contract provisions referred to in their necessary context.
The sub contract between the first named defendant McNamara and Company and the plaintiff is dated 5 January 2007. This
provides, at clause 1 of the subcontract, that the plaintiff is deemed to have notice of all the provisions of the main contract except
for prices. Clause 2 obliges the subcontractor to complete the works to the reasonable satisfaction of the contractor and of the
architect/engineer at the time being under the main contract and "in conformity with the reasonable directions and requirements of
the… programme agreed between the contractor and the subcontractor and approved by the architect/engineer, who in any case of
default in carrying out the program may himself directed the order in which the subcontract works shall be carried out." It is not
unreasonable to interpret this clause as enabling the contractor, the first named defendant, to give a direction to remove and replace
faulty materials. Under clause 3 the subcontractor agrees to comply with the provisions of the main contract and with the express
provisions of the subcontract as if all the clauses of both were set out in one document. Clause 6 provides that where the contractor
requires or authorises in writing any variation of or omissions from the subcontract works, or issues any instruction of the
architect/engineer or issues any verbal instruction or direction involving a variation, to be confirmed in writing within five days, these
are to be carried out. As I have previously implied; variations are not free, they must be paid for because they are outside what is
initially agreed. Clause 7 provides that any delay renders the subcontractor liable in damages. Defects are provided for in clause 8.
This reads:
The subcontractor shall within a reasonable time after receipt by him from the contractor or the architect’s/engineer’s or agents
instructions or a copy thereof relating to the same, make good all defects, shrinkages or other faults in the subcontract works due to
faulty materials or bad workmanship which the contractor (whether at his own cost are not) shall be liable to make good under the
main contract. Provided that where the contractor is liable to make good such defects, shrinkages or other faults, but not at his own
cost, then the contractor shall secure a similar benefit to the subcontractor and shall account to the subcontractor for any money
actually received by him in respect of same.
An issue has arisen, and here I am grateful for the expert assistance of Gerard O’Sullivan, quantity surveyor and barrister, as to how
this clause operates. It is reasonable to argue that in the event of defective works, that a subcontractor may be docked the cost of
defective goods. It can be argued that those defective goods when forming part of a larger job, such as a roof, should cause a
devaluation by way of certificate in themselves but that the subcontractor should not be docked the costs of replacement as under
clause 8 that subcontractor is liable to make them good at his own cost. However, another view is possible. It is also arguable that
where the parties, as here, agree the continuation of the work pending replacement for the purposes of early functionality, given the
problem of delay and the time coming up to Christmas at which this occurred, that this operates as a new contract between the
parties. Another view is also available that the cost of replacement, not just the cost of the defective material, may be withheld. The
point made on behalf of the plaintiff is not so strong of itself as to advance a claim of conspiracy. Under clause 11 the contractor is
obliged, after receipt of the subcontractor's detailed progress statement, the subcontractor having applied to the architect for a
certificate of payment and the inclusion of the amount of the value of the works and any variation as authorised for the benefit of
the subcontractor, to forward such certificate for payment. As a matter of fact, at all material times throughout the course of the
controversy that has been before me, it is apparent that the first named defendant, as main contractor, at all times was properly
applying for the payment by the second named defendant, as employer, of what was due to the plaintiff a subcontractor. This
included the uncertified glass works. In consequence, this includes the full remaining cost of the roof at €1.6 million plus VAT.
Clause 11 variously provides:
Fourteen days after the receipt by the contractor of any certificate from the architect/engineer the amount of certified
therein to be due in respect of the subcontract works shall be due by the contractor to the subcontractor and the
contractor shall within said time notified in writing to the subcontractor the amounts certified in the said certificate to be
due to him, any authorised variations thereof less retention money, which shall mean in this contract the proportion
attributable to the subcontract works of the money retained by the employer in accordance with the main contract and
less a cash discount ...
If the contractor shall fail to notify the subcontractor in accordance with the provisions of the foregoing subclause (B)
then the contractor shall on demand to him by the subcontractor furnished to the subcontractor details of all monies
certified for the subcontractor by the architect/engineer. Top If the contractor shall not furnish such details within 14
days after such demand the subcontractor shall be entitled to obtain these from the architect/engineer.
Payments made to the contractor in respect of work done and materials used by the subcontractor shall until received by
the subcontractor be deemed to be money or money's worth held in trust but without obligation to invest by the
contractor for the subcontractor to be applied in records payment of the subcontractor's account, subject always to the
rise of adjustment by the architect/engineer in the event of his certifying that adjustment is necessary.
If the contractor does not paid to the subcontractor the amounts certified by any certificate issued by the
architect/engineer to be due to the subcontractor within the period mentioned in subclause (B) thereof, then the
subcontractor-may (without prejudice to any other right or remedy) apply to the employer for and the employer may
make payment of the amounts certified to be due ... may, if payment has not been received within seven days after
receipt of payment by the contractor or within 28 days of the date of issue of the architect’s/engineer’s certificate
covering the amount due in respect of the subcontract works, after seven days notice to the contractor, suspend the
works for a period of 14 days and upon the expiry of the period, unless payment shall have been made in the meantime by
the contractor or by the employer direct, may determine the subcontractor's employment under the subcontract as from
the date of such expiry. ... may, without prejudice to other rights are remedies after 28 days from the date of the issue
of the certificate by the architect/engineered to the contractor covering the amount due in respect of the subcontract
works, be entitled to charge interest to the contractor on the amount included in such certificate that current bank rate
of interest on overdrafts until such time as payment is made by the contractor, or by the employer under subparagraph
(I) of this paragraph.
There then follows a detailed procedure in the event of a dispute. This is clause 11 (F) and it provides:
If the subcontractor shall feel aggrieved by the amounts certified by the architect/engineer or by his failure to certify or
failure by the employer to honour his certificate in whole or in part within this time period stipulated in the main contract
document, and then, subject to the subcontractor giving to the contractor such indemnity and security as the contractor
shall reasonably require, the contractor shall allow the subcontractor to use the contractor’s name and if necessary will
join the subcontractor as claimant in any legal proceedings by the subcontractor in respect of the said matters
complained of by the subcontractor.
This clause just quoted, the final paragraph of clause 3 defining relations between the parties and the arbitration provisions which
follow in the contract, are the main reasons for me concluding that the relationship between the parties was not governed by a
special relationship giving rise to liability in negligence due to a breach of duty but was instead governed by contract. It should also
be remarked that when this dispute first arose as to the proper payment for the plaintiff of €1.6 million and whether an abatement
could be applied instead of removal and replacement, Clause 11(F) enabled an immediate arbitration as to the appropriate
certification, with the plaintiff standing in the shoes of the main contractor, as against the second named defendant. I remain puzzled
by why this was not undertaken as by any other factor in the case. It was the appropriate response.
Clause 12 provides that the contractor is obliged, as far as it was legally possible, to obtain for the subcontractor all the rights and
benefits of the main contract in so far as these are applicable to the subcontract works. Set off is provided for in clause 13. This
allows the contractor to deduct from any monies due, any amount agreed by the subcontractor as due to the contractor or as is
awarded in litigation or arbitration in favour of the contractor. The contractor is entitled to set off against any money due “the
amount of any claim for loss and/or expense which has actually been incurred by the contractor by reason of any breach of or failure
to observe the provisions of the subcontract by the subcontractor, provided the amount of such set-off has been quantified in detail
and with reasonable accuracy by the contractor" in a notice in writing specifying this intention to set off a quantified amount which
must be given not less than 17 days before the money becomes due and payable. The argument is that whereas the glass was
defective and might have been set off that the cost of replacement was in the future. I see that argument but I do not see it as
being so strong as to advance the claim of conspiracy between the defendants. I see a contrary view as also being at least arguable.
On 31 August 2006 there was a meeting between McNamara and Company, as contractor, and the plaintiff as subcontractor. This
added a number of conditions to the contractual relationship between these parties. Among them was a clause which provided that
the main contract conditions would override anything to the contrary in the subcontract conditions. Clause 34 states:
"Notwithstanding anything to the contrary, we will not be liable for payment of monies due under the terms of the subcontract until
seven days after we have received such payment from the employer". This had been preceded by an invitation to tender by letter
dated 27 April 2006. Materials, goods and workmanship were provided for in the general conditions and contract particulars. These
were to be in accordance with the standards and quality of workmanship "given within the other documents forming part of the Works
package documents or by that given in instructions or directions issued in accordance with the provisions of the subcontract."
Minimum requirements were then set out, but these were not to override any of the requirements of the subcontract or the other
works package documents. Three subclauses are relevant and these are now set out:
Where and to the extent that products, materials and workmanship are specified to be approved or the subcontractor is
directed or instructed that they are to be approved, the same must be applied and executed in conformity with all such
requirements and in respect of the stated or implied characteristics either to the approval of the architect or to match a
sample approved by the architect.
Where samples are required for the approval of products or materials, the subcontractor shall submit samples or other
evidence of suitability and should not confirm orders for or use product or materials until approval has been given.
Approved samples shall be retained on site comparison with products and materials used in the subcontract works and the
subcontractor shall remove them were no longer required by the contractor.
Inspection or any other action by the main contractor or client’s representative must not be taken as approval of
samples, materials or products of work unless approval is given in writing.
In addition to these voluminous documents, a requirement specification of the employer was drawn up in April 2006. This applied to
the glazed roof and the glazed wall and door elements. This is where all the trouble began. Clause 1.3 provided that the glazing
contractor, and the plaintiff, would be entirely responsible for the roof achieving or exceeding the design and performance criteria.
Clause 2.5.4 provided for the two panes of glass to be partially occluded by dots inserted by silk-screening, of fritting, between the
layers of double-glazing. This was to cover the roof with 20 mm diameter dots on face one with an anti-slip finish colour to be agreed
with the architect. Samples were to be submitted prior to manufacture for review "by the contract administrator". Clause 5.3.1
required the drawings were to be submitted so as to ensure that they conformed to the specification and contract documents. The
purpose of this was to show that the proposed construction met the performance and visual requirements of the specification. It is
provided that the production drawings of the glazing contractors were not likely to meet this requirement. Under clause 11 the
plaintiff was to follow recommendations in the use of all materials, to the highest quality, and carry out the works in accordance with
the requirements of the specification. I have already quoted clause 6.6.4 as it is central to the dispute which broke out. In my view it
was not a dispute which should ever have broken out as the plaintiff had sole responsibility for the condition of the glass.
As a combination, these contract provisions support my finding that the plaintiff company was responsible for the condition of the
glass. There is no sustainable argument to the contrary.
So much for the relevant contract provisions.
I turn now to the allegation of conspiracy. There has been a gigantic amount of evidence as to how various documents ought to be
interpreted. This, at times, has impeded the course of the trial.
The meeting founding the alleged conspiracy was in fact held on 30 June 2008 and four people attended. On behalf of the first named
defendant, the managing director John McGowan, the eighth named defendant, was present. In addition, the fourth named defendant
was there as well on behalf of the first named defendant. The third named defendant, Bruce Shaw Project Management Ltd, was
represented by its principal John Balance, who is the fifth named defendant. Finally, Paul Newman, the seventh named defendant,
attended on behalf of the developer and employer Cedartree Construction Ltd, the second named defendant. It is to be noted that
Paul Hanby, the sixth named defendant, was not there at all. In the statement of claim in this case it is alleged that the court should
add him into the conspiracy because, as it pleads, it is reasonable to assume that others were acting for him. A court cannot act
upon what is reasonable as an assumption. The court can only act upon proof of what is probable. In this instance I am analysing
whether there is prima facie proof only. There is no case what ever made out against Paul Hanby and I want to say that now.
It must be remembered that this is not like a criminal case where one of the parties to a conspiracy has turned evidence for the
State, having been in effect an accomplice to wrong but now presenting himself in a penitent light. An example of that would have
been the breach of competition trial before Cooke J, as designated specialist civil and criminal competition law judge, in the Criminal
Courts of Justice in the People (DPP) v McNichoas and Others in May 2011. No such accomplice testimony exists. Any proof of a
conspiracy is based upon the interpretation of the interaction over the next two years from the date of the meeting of each of the
defendants, and in particular the fourth named, fifth named, sixth named, seventh named and eighth named defendants as
representing themselves and their corporate principals. It is argued on this basis that a conspiracy exists and it is urged on the court
that the acts and declarations of the co-conspirators in furtherance of the conspiracy are admissible each against the other.
Whereas this is a principle of criminal law, and is probably applicable to a civil conspiracy, without deciding that issue, the real
question before the court is whether or not the documents referred to as evidencing the conspiracy, and the circumstances
surrounding the actions and declarations of the conspirators, as so alleged, sufficiently establishes a prima facie case that a
conspiracy to unlawfully deprive the plaintiff of its money ever existed. I am taking that principle of cross admissibility as stated for
this purpose as making each such document admissible against each of the alleged conspirators because in thus acting I am taking
the plaintiff’s case, as I must, at its highest.
An interpretation has been placed on those documents to evidence on behalf of the plaintiff. Counter-interpretations have been put
on behalf of the three groups of represented defendants. This is all very well. Either the evidence is sufficient of itself to establish a
prima facie case of a conspiracy based on these documents, or it is not. Evidence can be given, for instance, to establish the factual
matrix within which a disputed contract was made. Evidence can also be given of what might have been in the mind of a testator
when making a will; the principle that the judge should construe the will by sitting in the testator’s armchair, or construe the contract
by placing himself or herself around the table where the contract is concluded. Thereby the words of a will, or in the same way the
words of a contract, can be seen against the correct backdrop. Interpretation, however, can only go so far. If the plain wording of
the documents evidencing a conspiracy is either inconsistent with the unlawful purpose alleged or does not establish a prima facie
case, the plaintiff must fail.
I turn therefore to the more important documents exchanged between the alleged conspirators and placed before the court as
evidencing that prima facie case of a conspiracy has been established. It is to be noted that hundreds of items of correspondence
between the parties among themselves and with others have been referenced in argument before the Court. I have decided which of
these is central to the best case that can be made of conspiracy. No argument has been left unconsidered. Possible interpretations
have been aired over four weeks as to these, and lots and lots of other, documents and I am aware of them all.
I rely on the evidence of Mr O'Sullivan, and on commonsense, that there is nothing wrong with the employer, the employer’s
representative and the contractor meeting together towards the end of any large development job with a view to settling the final
account. As of July 2008, around €5 million was due from the second named defendant to the first named defendant as a balance of
the overall contract price of around €115million. The principles of the second-named and first named defendants were in
correspondence with a view to setting up a meeting as the final payment, and as to amount given that there were claims as to delay
and water damage, and as to the timescale in which payment would be made. Within the first named defendant a view given on
behalf of John Ballance was exchanged to the effect that the plaintiff would be dealt with by him and his colleagues "and does not
need to be part of the final account settlement. They will look for replacement, but may end up accepting corrective work and a
credit." Even at this stage an alternative shaded glass is being discussed. It is apparent that a final resolution of the abatement or
replacement issue had not been resolved. On the morning of 30 June 2008 an early e-mail mentions leaks within the roof. A later note
indicates that "some items are being dispositioned ...Mero; Chesterbridge/ BSP will deal with Mero, including replacing the glass”. A
reduction in the contract price of € 500,000 had already been mooted by the employer, the second named defendant, but at the
meeting a further reduction was sought by the employer of €150,000. Prior to the meeting an intention to withhold the Mero money is
in evidence and that appears again in correspondence between those individuals within the third named defendant. That intention
arises on any reasonable construction of the documents because of the problem and not from anything that could be suggested to be
an improper purpose. Thus, on 2 July 2008 an e-mail between the parties sets out a memo of the final settlement. The revised final
account was about €115 million and additional discounts from that amount have been negotiated. The e-mail proceeds to indicate
that the "quantity surveyors on both sides will clear the actual amount outstanding now and the future release of retention ... we will
work with you to resolve the Mero issue". On 3 July 2008 it is noted between the parties to the meeting that there was "a firm
commitment to make the penultimate payments no later than five weeks from the date of the meeting last Monday. ... On Mero, we
will continue to work with Chesterbridge and BSP to resolve the remaining issues, but the lead on these negotiations, and decisions on
payment, glass replacement etc will be taken by Chesterbridge/BSP."
I cannot see that this is wrong or is evidence of anything other than a continuing intention to try to work through a problem. The sum
agreed at the meeting was €5 million to be paid within five weeks. This notional sum included €1.6 million due to Mero. The fourth
named defendant and the eighth named defendant corresponded on 4 July 2008 and made reference to an e-mail concerning final
settlement sent by the fifth named defendant. In that e-mail he refers to "the intention, as noted at the meeting, would be to make
the penultimate payments to you within a maximum of five weeks." There is a reference back to this in the e-mail as the fourth point
mentioned: "I am astounded at number four John Ballance minutes attached-"the intention is to make an ultimate payment of c€5
million within five weeks". My understanding was that they were confirming it would be paid in five weeks, and that this was when it
would be scheduled. What is the payment period in the contract? Can we ensure that the quantity surveyors get together quickly to
agree the final amount of payments certified as referred to in number 37."
It is argued that this is evidence of a conspiracy by the defendants to cause Cedartree Construction Ltd, the employer and second
named defendant, to pay €5 million to Michael McNamara and Co, the main contractor and first named defendant, which some would
include the €1.6 million due to the plaintiff and that the defendants would keep this money for themselves. This allegation is extremely
improbable for a number of reasons.
Firstly, it is highly unlikely that the second named defendant would seek a reduction of €150,000 on the sum due by it while at the
same time entering into a conspiracy to unnecessarily pay out €1.6 million in respect of the work on the glass canopy which would
never be paid by the first named defendant and so kept by them, or kept substantially by them, while batting down the plaintiff to an
unreasonable sum through stringing the dispute out. No one sensible would agree to that unless there was something in it for them.
There is no evidence that there was any such benefit or prospective benefit. Conspicuously absent is any agreement to divvy up
unlawfully retained monies. This alleged agreement would involve completely wasted monies from the point of view of the second
named defendant.
Secondly, an e-mail of 4 July 2008 between the fourth named defendant and the eighth named defendant refers to the hope that
something might be saved in monetary terms on other works to do with paving in the courtyard area under the glass roof and that
this "will in some way alleviate the ambush last Monday". This is not indicative of a cosy agreement between the parties to the
meeting to do the plaintiff down. Prior to the meeting of 30 July 2008 reference had been made in correspondence to a total due
which would include a €1.6 million sum due to the plaintiff. On 18 July 2008, however, the sum due is reduced to take account of the
fact that the money due to the plaintiff will not be claimed. It is clear from other correspondence that the nature of the glass and an
issue as to leaking, for which the plaintiff was probably not entirely responsible but which was important, remained live from
correspondence in the previous year.
I need to refer back at this stage. An e-mail sent by the third named defendant on 19 October 2007 indicated their attitude. This
referred to the necessity to prepare a detailed estimate for the replacement of the glass. The e-mail goes on: "as advised the
BSP/McN outline budget for the replacement of the glass is €1 - €1.5 million. At this point in time we will not be certifying additional
monies until the parties to the contract resolve this issue." This correspondence does not rule out the future certification, when
proper, of the sum due for the glass canopy. An earlier exchange on that day refers to defective glazing. It states an argument made
on behalf of the plaintiff: "as per the comment in my e-mail yesterday: monies have been withheld for an alleged defect to the
glazing, however at the meeting yesterday (Wednesday) the glass manufacturer stated that they did not accept that the glass was
defective. We therefore consider that it is premature to deduct money from our certificate due to this matter." On 31 October 2007
the third named defendant had asked the plaintiff when they would be "issuing a method statement and program for the glass
replacement as discussed at the last client meeting. As advised this information is required to enable us to prepare a detailed
estimate for the glass replacement." The issues as to the glass and its replacement and the roof and the leaks through it continued to
dog relations between the parties at the time of the conspiracy and well beyond. It was easily to be resolved by invoking the
arbitration clause.
Returning to 2008, approximately 3 weeks after the alleged conspiracy meeting, the first named defendant wrote to the third named
defendant confirming the agreement on the final account which had been reached in the sum of €115 million. A paragraph in the letter
states: "We note the amounts for nominated sub-contractors are agreed on the basis of full consideration of all sums due to these
subcontractors under the sub contracts." Was this an attempt by the first named defendant to get monies due to the plaintiff and
keep it for themselves, or later divvy it up among the others? It is immediately apparent that this is not so. Both prior and subsequent
correspondence indicates that the sum to be claimed does not include the money due to the plaintiff. An invoice issued by the first
named defendant on 5 August 2008 makes reference to monies due "as per architect’s certificate" and claims an amount due of €3.5
million. Certificate number 35 from the third named defendant of 6 August 2008 reflects that. It is hard to see that this was not the
right way to proceed under the contract; as this specifies no payment until certification, but that the subcontractor if dissatisfied
could invoke clause 11(F) of the subcontract and arbitrate any dispute on non-certification or under-certification with the employer
directly. Reasons have been given in evidence for not invoking this clause: some of these are self-contradictory. Whereas it might be
said that litigation of any kind is not a good manoeuvre in business, this dispute was very unlikely to go away. The clause should have
been invoked by the plaintiff once it adopted the position that it was not going to replace the glass. Correspondence of 22 August
2008 indicates that an invoice had been submitted by the first named defendant based on the figures. I do not regard the e-mail of
21 August 2008 within the first named defendant as being evidence of conspiracy. No one can now remember what the e-mail meant.
It reads, as between the fourth named defendant and the eighth named defendant: "Kindly advise who is looking after the Change for
Paul Newmann, regarding 3.5 million payment." I am asked to take a meaning from this that “the change” referred to was the €1.6
million due to the plaintiff. There is no firm, or even sufficient, foundation here on which a court could begin to act. On 13 November
2008 an issue was raised that the first named defendant should begin legal proceedings against the second named defendant for an
outstanding sum which would have included the €1.6 million due to the plaintiff. As it turned out, this did not happen. €2 million was
paid on the 29 September to the first named defendant by parties associated with the second named defendant followed by a
€100,000 payment on the 4 November 2008. On 17 November 2008 it is proposed to pursue a balance owing of about €1.02 million.
This does not include the €1.6 million due to the plaintiff. This conspiracy allegation just does not hang together.
It is also argued that the timing of the revelation that there had been a final account meeting on 30 June 2008 is indicative of a
conspiracy between the defendants. In that respect I have been referred to the affidavit of John McGowan sworn in the proceedings
between the first named defendant and the second named defendant for the purpose of seeking summary judgement and dated 4
March 2009. This does not in any sensible way advance matters. The documents allegedly evidencing a conspiracy were supposed to
have been exhibited in that affidavit but not read out in court, the plaintiff being present through a watching brief. This, however, is
what often happens in a busy court list. In September 2010, having pressed for the release of relevant documents, including those to
which I have made reference, these papers were formally discovered to the plaintiff.
Did the fact that there had been a final account settlement meeting come as a surprise to the plaintiff? There had been a meeting
between representatives of some of the parties in Kilkenny on 22 August 2008. A note by David Barrow indicates that leaking had by
then become more important than the banding issue. Another meeting had been held on 31 July 2008, prior to that meeting, where
within the plaintiff a strategy had been involved to minimise the responsibility of the plaintiff in respect of the banding issue, to
emphasise that no viable commercial alternative existed, and to press the position that the remedy for aesthetic defects lies in
damages and not in replacement. As will have emerged from earlier references, the meeting in Kilkenny revolved around an alternative
screen printing process. The document states:
To assist in defending Mero/Romag position in the forthcoming meeting with John Balance, Ken White is to produce a technical paper
to dismiss the samples produced by Hall Print Solutions as being viable alternatives. David Barrow is to present this paper from Ken
White at the meeting.
The fourth meeting took place near Heathrow airport in London on the 15 September 2008. It is clear that this meeting was held with
a view to resolving the financial issues between the plaintiff and the main contractor and the employer, through the employer’s
representative. A note made by David Barrow at that meeting reads under the heading "review of nominated": "as BS has settled a/c
with McN - problems of elongation payment etc." An offer of abatement was made by the plaintiff of €250,000 in return for a prompt
payment of €1 million. This offer was not sufficient to settle matters between the parties. It was always unlikely that it would never
have been as the glass had been charged by the plaintiff to the job at more like €600,000. The note quoted leads on its own to a
possible interpretation that the writer was aware that a final settlement had been reached between the first named defendant in the
second named defendant. This was not treated with alarm by the plaintiff and nor is that surprising. I do not accept that an
experienced contractor would find it sinister than a main contractor, the employer and the representative of the employer would seek
to conclude a final account upon the practical completion of almost all the works in a major development. Neither is it suspicious that
the total amount that would eventually be due would be tabled for agreement. Any reference to a penultimate payment does not
exclude that whatever sum is eventually agreed in a disputed account with a subcontractor would be included in the ultimate
payment that would incorporate retention moneys. On the contrary, this has not been established as being abnormal.
I am not impressed by this. Even less is the complete destruction of the surprise and concealment point, mooted as objectives of the
conspirators, by reference to a letter written from David Barrow on behalf of the plaintiff to the first named defendant and dated 21
December 2009. One paragraph in this explicitly makes reference to the fact that the plaintiff had been told that there had been a
final settlement of the main contractor’s account: “Our understanding is McNamara have had their account settled in full by the
Employer with the exception of the [Mero Schmidlin UK] nominated account.”
The case of conspiracy falls apart. There was no conspiracy to abuse contractual relations to keep the plaintiff out of its money and
there was no conspiracy to pay the first named defendant an effectively free sum of money from the second named defendant on the
understanding that the plaintiff would never get it.
In this case, it is impossible not to have sympathy for the plaintiff. But that is not the only factor. This entire matter occurs against
the backdrop of the over-ambitious projects in retail and residential accommodation that characterised the disastrous undermining of
the Irish economy during the years 2000 – 2008. These projects could only be successful were there people to shop in them and
reside in them. Those people could only have the kind of money to spend that was being asked for the rent of retail units and the sale
of residential properties had they worked in industries or services of a productive kind. Through over-attractive and unreal prices for
property, the economy was slewed away from production and towards an over-reliance on non-productive enterprises.
Many have lost heavily. The plaintiff cannot recover €1.6 million from the first named defendant, having been paid €1.4 million,
because the first named defendant is now in receivership. The first named defendant is out of its contract money as developer at
least €1 million and probably double that and more because of retention monies that remain outstanding. The second named
defendant, the papers I have read in this case indicate, has had to rent the retail McDonagh Junction units cheaply or sell residential
units at bargain prices and is a sorry entity as opposed to very profitable one. The third named defendant was owed substantial fees
but had to take a discount due to a creditor’s voluntary arrangement of about 48%. The National Assets Management Agency has
taken over the first named defendant and the people of Ireland are the ultimate carriers of what is now a severe burden of debt.
None of this makes any difference to the issue as to whether there is prima facie proof of a conspiracy.
It is all very unfortunate, but there was no conspiracy to unlawfully, by whatever means, deprive the plaintiff of what was due to it.
The order for costs which I shall make, having heard argument, is to award each of the defendants their costs as against the plaintiff
as Order 99 of the Rules of the Superior Courts requires. On the unsuccessful motion for security for costs brought at the
commencement of the action, over one and a half of the fourteen days of the trial, by the second named, sixth named and seventh
named defendants, these costs are awarded to the plaintiff. Presumably, there can be a set off but the calculation of the balance is
not for me. Since enforcement of court judgments has become easier within the European Union, the principles governing an
application for a defendant against a foreign defendant should more concentrate on similar principles to those set out in s. 360 of the
Companies Act 1963, as this application did. There will be a stay on the costs order but only for four months and any extension
thereafter is a matter for the Supreme Court.