Legislator Rechtsprechung & Gesetzgebung
IEHC 467 ECLI:IE:HC:2009:467 KI-generiert

High Court dismisses employer's claim to arbitrate third-party defect claims due to privity rule exceptions not met.

Geschäftsnummer IEHC 467
Gericht / Behörde
Rechtsordnung Irland (IE)
Entscheiddatum
Ausgang Abgewiesen (Dismissed)

Legislator-Zusammenfassung

KI-generiert

The High Court dismissed the employer's request to include third-party claims for building defects in an arbitration between the contractor and employer. The employer argued that collateral warranties should be enforceable by them, but the court found no exception to the privity rule applied. The court held that allowing the employer to claim on behalf of non-parties would create legal black holes and potential double liability for the contractor.

Legislator-Regeste

KI-generiert

Arbitration Act 1954 s. 35(1); Rules of the Superior Courts, 1986 Order 62: The employer cannot claim third-party rights for defects in an arbitration unless a recognized exception to the privity rule applies, which was not found here.

Schlagwörter

KI-generiert
privity of contract collateral warranties arbitration privity third party claims special case stated building defects contractual liability Drittansprache

Zitierte Gesetzesbestimmungen

KI-generiert
Arbitration Acts 1954 to 1998
IN THE MATTER OF THE ARBITRATION ACTS 1954 TO 1998 AND
Section 35(1) of the Arbitration Act 1954
Under s. 35 of the Arbitration Act 1954, he has stated
Order 62 of the Rules of the Superior Courts, 1986
s. 35 of the Arbitration Act 1954
Under s. 35 of the Arbitration Act 1954, he has stated
KI-generiert

Fragen Sie sich, wie dieser Entscheid auf Ihren Fall anwendbar ist?

Prüfen Sie diesen Entscheid zusammen mit Bundesrecht, kantonalen Erlassen, Kommentaren und Folgeentscheiden in Legislator AI.

Fall in Legislator öffnen →

Volltext

Neutral Citation Number: [2009] IEHC 467

THE HIGH COURT

2009 242 SS

IN THE MATTER OF THE ARBITRATION ACTS 1954 TO 1998 AND

IN THE MATTER OF SECTION 35 (1) OF THE ARBITRATION ACT 1954

AND IN THE MATTER OF ORDER 62 OF

THE RULES OF THE SUPERIOR COURTS, 1986

AND IN THE MATTER OF A SPECIAL CASE STATED BY AN ARBITRATOR IN THE COURSE OF A REFERENCE TO ARBITRATION

BETWEEN

BOWEN CONSTRUCTION LIMITED

PLAINTIFF

AND

KELCAR DEVELOPMENTS LIMITED

RESPONDENT

JUDGMENT of Mr. Justice Ryan delivered on the 16th day of October, 2009

1. Blarney Golf Resort, Co Cork consists of a golf course, a clubhouse, a hotel and 56 cottages. The course is owned by

Kelcar Lands Ltd. and the clubhouse and hotel by a group of private investors. Eighteen of the cottages have been sold

while the remaining 38 continue to be held by Frank and Derek McCarthy, the shareholders in Kelcar Developments Ltd.,

party to these proceedings. The resort is operated by BGR Limited, a wholly owned subsidiary of Kelcar.

2. The construction work for the development was carried out pursuant to a building contract between Kelcar

Developments Ltd. [Kelcar] as employer and Bowen Construction Ltd. [Bowen] as contractor. Kelcar transferred the

ownership of the buildings to others, including associated persons and companies, on foot of development agreements.

Under one of the terms of the building contract, Bowen agreed to execute collateral warranties to give the transferees of

the buildings similar rights to sue for defects as were contained in that agreement. The development agreements also

contained warranties by Kelcar as to the quality of the buildings.

3. Pursuant to the undertaking in the building contract Bowen executed collateral warranties under seal in favour of the

private investors, who own the clubhouse and the hotel, which conferred on them the right to pursue the contractor for

defects. However, in the case of the cottage owners, although Kelcar and Bowen agreed that such warranties would be

given, they have not, in fact, been executed. Bowen submitted that it is willing do to so but has not been called upon to

execute any such warranty. Kelcar does not contest this proposition.

4. The arbitrator in a dispute under the building contract for the development has sought directions from the court in

respect of issues that have arisen in the course of the hearing. Under s. 35 of the Arbitration Act 1954, he has stated

questions of law in the form of a special case for the decision of the court. The legal issue raised is whether the employer

who is party to the building contract can counterclaim and set off in the arbitration the costs of remedying defects, and

anticipated consequential losses arising therefrom, in circumstances where those losses have been or will be sustained by

other persons or companies who were not parties to the building contracts. The question has not been the subject of a

written decision by a court in this jurisdiction but the English Courts have done so and the House of Lords considered the

question as recently as 2001. In this reference, Bowen Construction Limited [Bowen] is the contractor and Kelcar

Developments Limited [Kelcar] the employer in the building contract.

5. Kelcar does not have any legal interest in the buildings that have the alleged defects; neither does it operate the

resort. The buildings are owned by different but (for the most part) associated persons or companies and the resort is

operated by a wholly owned subsidiary company, BGR Ltd. When these issues came to light during the proceedings, the

arbitrator gave leave for Kelcar to amend its points of defence and counterclaim, but he rejected an application to join

BGR as a party in the arbitration. The amended pleading set up the cost of remedying the defects in the buildings, plus

projected consequential losses ascribed to BGR, by way of counterclaim and set off, in reduction of the claim for extra

payment under the contract. An amended answer by Bowen denied the legal validity of these claims on the grounds that

Kelcar was not entitled to make them because it had not and would not sustain any losses itself and that the parties that

had done so or would do so were not parties to the building contract.

6. It is claimed that there were serious defects in the buildings, particularly in the construction of the roofs, giving rise to

a substantial claim for compensation in respect of repair costs and consequential loss. The claim for loss includes that of

BGR which, it is said, will have to close the resort for the duration of the repair work and will suffer disruption of business.

Bowen does not admit that any of these losses has arisen or will arise. It is however accepted that, for the purpose of

answering the questions posed by the arbitrator, it is to be assumed that there were defective roofs and that they will

give rise to the alleged losses, or some of them.

7. The contractor relies on the doctrine of privity of contract. Only a party to a contract can sue for breach. And a

claimant can only recover losses that he has sustained or will sustain. Kelcar counters this argument on two grounds,

which, to say the least, are not wholly consistent. In written submissions, it contends that the facts of the case come

within an exception to the privity rule that has been recognised in a series of English cases, which reflect the

development of the Common Law and ought to be followed. In oral argument on the reference, Counsel for Kelcar adopted

these written submissions but also made the case that the provisions of the building contract itself enabled the third

party losses claims to be maintained. If this latter submission is correct, it means that it is unnecessary to rely on the

privity exception and it would also seem that the amendments sought by Kelcar in the arbitration would not have been

needed, because the claims could simply have been advanced under the building contract. I consider the second of these

arguments before turning to the privity issue.

8. This contention is that clauses 21(A) and 21(B) apply to losses sustained by third parties and authorise the employer

to make a claim in respect of such losses under the terms of the contract. Section 21(B) deals with insurance against

damage to persons and property and it is contended that this has relevance because it requires a building contractor to

arrange for insurance against the liability that is described in s. 21(A) but it does not appear to have any other

significance. Clause 21(A) at para. (i) imposes liability on the contractor and an obligation to indemnify the employer in

respect of any loss, damage or injury to personal property that “arises out of or in the course of or by reason of the

execution of the works” if that is due to negligence or fault on the part of the contractor or a sub-contractor or their

servants or agents. Paragraph (iii) excludes the building works themselves from the above liability up to the date of

practical completion or earlier if the contractor’s function is terminated. It is suggested that these provisions introduce a

liability for loss or damage suffered by third parties after the date of practical completion or determination of the

contractor’s employment.

9. I cannot accept this interpretation. These contractual provisions in my view are intended to apply to entirely different

situations from the one proposed. They deal inter alia with personal injury and damage to personal property that arise out

of or in the course of the works, due to the negligence of the contractor or a sub-contractor or a servant or agent of

either. For obvious reasons, the contract imposes or recognises that liability on the part of the contractor and provides

for an indemnity for the employer and this liability comes to an end when the building work is practically completed. A

reading of s. 21(B) which relates to insurance, confirms this meaning. It is simply a misreading to think that Clause 21(A)

extends the contractor’s liability to parties claiming losses by reason of defective execution of the building work, when

para (iii) expressly excludes the works themselves. The time period specified is a limitation of liability not a commencement

date.

10. Turning to the other argument made by Kelcar in its written submissions, this is that the case comes within the

exceptions to the privity rule that have been recognised by the English Courts in order to avoid injustice. Kelcar says that

Bowen’s argument would result in a situation where the building contractor would be “entitled to escape all liability for its

wrongdoing”, i.e. on the agreed assumption for the purpose of this case that there are defects resulting from breach of

contractual obligations.

11. The rule that a claimant cannot recover more than the amount required to compensate him for his own and not

another’s loss can result in injustice, as the 30th edition of ‘Chitty on Contracts’ remarks:-

“because it can give rise to what has been called a ‘legal black hole’, that is, to a situation in which the promisor

has committed a plain breach which has caused loss to the third party whom the contracting parties intended to

benefit, but none to the promisee, and in which no other remedy (than damages for the third party’s loss) is

available against the promisor”. (Para. 18-051)

12. The loss suffered by the aggrieved person who is not a party to the contract can fall into this legal black hole where

the person does not have a remedy. In order to avoid this unjust situation, there are exceptions to the general rule.

13. The area of exception that is relevant to this case begins with Linden Gardens Trust v. Lenesta Sludge Disposals

Limited [1994] 1 A.C. 85. The employer in that case under a building contract succeeded against the contractor,

notwithstanding the fact that the site of the building work had been transferred to a third party. The contractor’s

argument that no loss had been suffered by the employer as he was no longer owner of the land when the alleged

breaches occurred, and was therefore entitled to no more than nominal damages, was rejected in the House of Lords on

two distinct grounds.

14. The so-called broader ground, which was proposed by Lord Griffiths, was that the employer was entitled to have the

contract he had entered into performed by the other party so as to give the employer “the benefit of the bargain which

the defendant had promised but failed to deliver”. He said that the court would have to be satisfied that the repairs had

been or were likely to be carried out, but subject to that, the disappointed party was entitled to have the contractual

obligation fulfilled in accordance with what had been agreed.

15. The other members of the House of Lords in the Linden Gardens case based their decision on what is known as the

narrower ground. They applied the exception that was recognised in the Albazero case [Albacruz (Cargo Owners) v

Albazero (Owners) (The Albazero) [1977] A.C. 774], the rationale being that the contractor could foresee that parts of

the new development were going to be occupied and possibly purchased by third parties, so that it could be foreseen

that damage caused by a breach would cause loss to a later owner. The contractor could also foresee that a later owner

would not have acquired rights under the building contract against the contractor since that contract expressly prohibited

assignment by the employer without the contractor’s written consent, which had not been sought. At para. 18-053,

Chitty summarises the Linden Gardens case as follows:-

“The effect of the Linden Gardens case was thus to extend the scope of the Albazero exception from contracts for

the carriage of goods by sea to contracts generally, but it was consistent with two factors which had restricted

the scope of that exception: namely, that (a) the loss or damage was caused to property which had been

transferred by one of the contracting parties to the third party; and (b) the third party had not acquired any rights

under the building contract and it was foreseeable (by reason of the prohibition against assignment) that he would

not do so.”

16. In Darlington BC v. Wiltshire Northern Limited [1995] 1 W.L.R. 68, the Court of Appeal effected an extension of the

Linden Gardens decision to a situation in which there was no transfer of the property to the third party and this extension

was subsequently approved by the House of Lords. This removed limb (a) of the restriction in the Linden Gardens decision

but it left limb (b) in place.

17. The latest case is a decision of the House of Lords, Alfred McAlpine Construction Limited v. Panatown Limited [2001]

A.C. 518. The building contract was made, not between the building contractor and the company that owned the site

but, for tax avoidance reasons, between the contractor and another company that was associated with the owner of the

site and which was the employer under the building contract. A separate contract was made between the owner of the

site and the contractor which imposed obligations on the contractor that were broadly similar but not precisely the same

as those in the building contract and one of the differences was that it did not include an arbitration clause. In a

subsequent arbitration, the employer claimed damages from the contractor who resisted the claim on the basis that the

employer could recover no more than nominal damages since it was not the owner of the property. The House of Lords,

by a majority, upheld the contractor’s argument and so rejected the employer’s claim for substantial damages in respect

of the owner’s loss.

18. The House considered whether the Linden Gardens grounds, either the broader or the narrow ground, supported the

employer’s claim. Chitty comments that the Linden Gardens exception did not apply:-

“because the duty of care deed gave the owner an independent contractual right against the contractor.”

19. The Linden Gardens exception was not needed because there was no risk of a legal black hole when the third party

had its own contractual rights against the party in breach.

20. The majority in the House of Lords in the Panatown case also held that the rights enjoyed by the sustainer of the

loss, pursuant to its separate contract, also precluded the employer from recovering damages under the broader ground

advanced by Lord Griffiths in the Linden Gardens case. Chitty supports this aspect of the judgment, for two further

reasons:-

“First, the creation of extension of exceptions to the general rule that a party can recover damages only in respect

of its own loss is, and should be, driven and limited by necessity: that is, by the need to guard against the risk of

‘legal black holes’ of the kind described above; and in the Panatown case, there was no such risk. Secondly, the

decision gives effect to the ‘contractual scheme’ created by the parties; and this point, so far from being

undermined by the fact that the contractor’s obligations to the owner under the duty of care deed were not

precisely conterminous with his obligations to the employer under the building contract, is reinforced by this fact.”

(Para. 18-056)

21. It follows from all this that there is no support in English authority for abandoning the general rule of privity of

contract so as to enable a party to an arbitration to claim losses sustained, or allegedly sustained, by other parties in

circumstances where those other parties enjoy their own legal rights to claim in respect of losses that they may have

sustained.

22. Kelcar’s Written Submission seeks to distinguish this case from McAlpine v. Panatown [2001] 1 A.C. 518 by relying on

the separate development agreements that Kelcar made with the original owners of the 56 golf lodges (who still own 38 of

them) and the owners of the clubhouse and hotel. The similarity with that case, however, is that the latter group can

recover damages for defective construction from the builder under the warranty agreement. As to the lodge owners, the

builder is bound by agreement to provide a similar warranty but that has not been executed to date.

23. Kelcar then relies on what is called the “broader ground” of liability in the building cases. This was the basis of the

reasoning of Lord Griffiths in his speech in Lindon Gardens Trust v. Lenesta Sludge Disposals Limited [1994] 1 A.C. 85. It

is that the employer in a building contract has a right to have the contract performed according to its terms and is

therefore entitled to sue for substantial and not merely nominal damages in the event of breach, despite not being the

owner of the building at the time of the claim, provided it is clear that he actually intends to carry out the repairs. Lindon

Gardens Trust was a case where the claim was allowed as “a remedy where no other would be available to a person

sustaining loss which under a rational legal system ought to be compensated by the person who has caused it.” – speech

of Lord Browne-Wilkinson at pp. 114 to 115.

24. In respect of the anticipated loss by BGR, Kelcar argues that there could be a legal black hole whereby BGR would

suffer loss attributable to the breach of the building contract, but nevertheless be deprived of any remedy. The remedy

proposed is for Kelcar to be entitled to make the claim. Kelcar submits in the alternative that it is entitled to abatement of

the amount found due to Bowen in the cost of repairs to the buildings.

25. Bowen submits that the doctrine of privity of contract is well established in Irish law and casts doubt on whether the

English authorities cited above ought to be followed, in so far as they afford any basis for Kelcar’s argument. I do not

think that Burke (A Minor) v Dublin Corporation [1991] 1 I.R. 341, which is relied on, has any application to the issue

here. I am satisfied that the consensus of the English cases represents the development and application of existing

principles of the Common Law to new situations, for the purpose of avoiding injustice, and that it ought to be followed.

26. Subject to the above reservation, the contractor relies on the McAlpine v Panatown [2001] 1 A.C. 518, citing the

speech of Lord Browne-Wilkinson at p. 531 of the report at 531H et seq:-

“If the contractual arrangements between the parties in fact provide the third party with a direct remedy against

the wrongdoer the whole rationale of the rule disappears.”

27. It seems to me that the cases cited, insofar as they are relevant to the issues in the case, yield to the following

propositions:-

• Privity of contract together with the general prohibition on claiming for loss or damage sustained by third parties

are subject to exceptions in order to avoid injustice.

• In building contract cases, the exception applies to cases where there would be a “legal black hole”, meaning that

the person who sustains the loss would be without any remedy in law, the person entitled to sue would not be able

to prove substantial loss and the party in breach of contract would go scot-free.

• Where the party suffering the loss has a right of action against the person in breach of contract, the exception

does not apply – Alfred McAlpine Construction Limited v. Panatown Limited [2001] 1 A.C. 518.

• On the “broader ground” that Lord Griffiths applied in Lindon Gardens Trust, the contracting party has a right to

sue for failure to provide what was contracted for, if it is shown that he intends to do the remedial work but that

basis of claim has not been adopted in other cases. If it were to be adopted in a case where it was not necessary

in order to avoid injustice because there was no other remedy available, it would give rise to a problem as to the

status of any damages that might be awarded to the employer in respect of repairs or consequential losses

sustained by other parties.

28. In this case, the owners of the clubhouse and hotel have their own remedy against the building contractor. The lodge

owners are entitled to a similar remedy but it has not been provided to date. Counsel for the builder has acknowledged its

willingness to do so for the lodge owners. It follows in my mind that there is no legal black hole in this case. If the builder

reneged on the undertaking to furnish the lodge owners with the agreed protection, there would be a black hole and

Kelcar could sue for specific performance of the agreement to provide the warranty, which would I think be the most

appropriate relief and, in the alternative for the cost of repairing the lodges.

29. The issue to be decided in the reference is whether the facts bring the case within the exceptions to the rule of

privity of contract. Can Kelcar as the employer party to the building contract claim in the arbitration for the alleged

defects in the work and for anticipated consequential losses by other associated persons or companies? In my view the

case does not constitute a recognised exception or an exception that ought to be recognised. No legal black hole exists.

In the absence of any refusal by the builder to furnish the collateral warranties to the cottage owners, I cannot see how

the employer is entitled to pursue the claims of third parties.

30. It seems to me that there are substantial practical objections to permitting the employer to put forward in the

arbitration the claims of the third parties. If Kelcar claims in respect of the defects and projected losses, does that

operate as a bar to any claims by the private investors who own the hotel and clubhouse, the people who own the 18

cottages that have been sold, the owners of the remaining 38 cottages and BGR Ltd., the operator of the whole resort?

None of those is a party in the building arbitration between Kelcar and Bowen, so how can their claims be heard and

determined? There would be nothing to prevent any of them from bringing a claim against Bowen in respect of alleged

defective workmanship and/or consequential loss. It would be no answer for Bowen to say that it had already paid out the

money on foot of a proceeding to which the claimants were not parties. Neither is it reasonable to suggest as Counsel did

that, since the parties and companies are interconnected, their separate identities can be ignored, since that represents

the “reality of the situation”.

31. A party is best left to make its own case for loss or damage and can be disadvantaged by having another make that

case on its behalf. The whole point in this case of seeking to set up these claims for repairs and anticipated consequential

loss is to wipe out Kelcar’s liability to Bowen under the arbitration pro tanto. In my view, that is the potential black hole

because any compensation that was due to other parties could disappear into the reduction of Kelcar’s contractual

liability.

32. My conclusion is that this is not a case that is within the exceptions to the privity rule. This is consistent with the

consensus of the authorities that were cited and it accords with logic. To hold otherwise would be to introduce a new

ground of exception and would itself produce legal difficulties and potential injustice, including the risk of double liability on

the part of the contractor.

33. As to the particular issue of BGR’s anticipated consequential loss, it seems to me that, if it is claimable under the

building contract, it is similarly claimable under the rights that have been conferred on the clubhouse and hotel owners

and on the rights to which the lodge owners are entitled. BGR’s position therefore is unaffected.

34. I answer the questions posed in the case stated as follows:-

3.2.1 In the light of the fact that Kelcar is not the owner of any of the buildings in respect of which remedial work

will be required, can Kelcar claim in its own right the costs of those remedial works?

Answer: No.

3.2.2 Not applicable because of answer to 3.2.1

3.2.3.1 Not applicable because of answer to 3.2.3.2

3.2.3.2 If BGR is, as a matter of law, entitled to recover damages from Bowen, can those damages be claimed by

Kelcar in these proceedings?

Answer: No.

3.2.4. Not applicable because of answer to 3.2.3.2