Third-party proceedings set aside for failure to serve notice as soon as reasonably possible under s. 27(1)(b).
Legislator-Zusammenfassung
KI-generiertThe court set aside the third-party proceedings against McElroy because the third-party notice was not served as soon as reasonably possible. Markland and Cantier argued that the delay was justified by the dormant status of Cantier and the complexity of the construction dispute. The court rejected these arguments, holding that the obligation to serve notice arose immediately upon the plaintiff's claim, and the delay created a multiplicity of actions contrary to judicial efficiency.
Legislator-Regeste
KI-generierts. 27(1)(b) of the Law of Property Act 1922; s. 27(1)(b) of the Law of Property Act 1922: A third-party notice must be served as soon as reasonably possible; failure to do so renders the third-party proceedings liable to be set aside.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertZitierte Rechtsprechung
KI-generiertVerwandte Entscheide
KI-generiertVolltext
Neutral Citation Number: [2007] IEHC 255
THE HIGH COURT
RECORD NO. 2003/6781 P
BETWEEN
DENIS MURNAGHAN
PLAINTIFF
AND
MARKLAND HOLDINGS LIMITED
FIRST NAMED DEFENDANT
CLAIMANT
AND
CANTIER CONSTRUCTION LIMITED
(IN VOLUNTARY LIQIDATION)
SECOND NAMED DEFENDANT
FIRST NAMED RESPONDENT
AND
N. McELROY ASSOCIATES LIMITED
TRADING AS McELROY ASSOCIATES CONSULTING ENGINGEERS
THIRD PARTY
SECOND RESPONDENT
Judgment of Miss Justice Laffoy delivered on 10th August, 2007.
The application
1. By order of this Court made on 31st March, 2006 it was ordered that the third party (McElroy) be joined as a third party in these
proceedings on the basis that it would be joined with the second named defendant (Cantier) as co-defendant in the claim for
contribution and indemnity of the first defendant (Markland) in these proceedings. On this application McElroy seeks to set aside the
third-party proceedings.
Factual and procedural background
2. In these proceedings, which were initiated by plenary summons which issued on 5th June, 2003, the plaintiff sought damages for
loss he had incurred as a result of damage to his residence at 5 Pembroke Place, Dublin 2, caused by the construction of a building on
an adjoining site at No. 70 Leeson Close, Dublin 2. Markland was the owner and developer of the site at No. 70. Cantier was the
building contractor retained by Markland to construct the building. McElroy was retained by Markland as structural engineers to advise
on the construction of the building.
3. On the day on which the plenary summons was issued, the plaintiff applied for and obtained an interim injunction restraining the
defendants from carrying out any further works on No. 70. The subsequent application for an interlocutory injunction in the same
terms was vigorously defended by Markland. Eventually, agreement was reached on 25th July, 2003 between the plaintiff and
Markland, which resulted in the plaintiff’s motion for an interlocutory injunction being struck out. An important element of that
agreement was that Markland agreed to facilitate a joint inspection by the engineers of the plaintiff and Markland of the foundations
of both buildings. The parties also agreed a timetable for the procedural aspects of the proceedings with a view to securing an early
trial, in accordance with which Markland’s defence was delivered on 9th September, 2003.
4. The inspection of the foundations took place between 11th and 15th September, 2003. The reports of McElroy put before the
court by it on this application disclose that it informed Markland on 18th September, 2003 that it was common case between
Markland’s advisers, including McElroy, and the plaintiff’s engineer and architect that they were unable to observe a point where the
foundations of No. 70 separated from the foundations of No. 5. In a fuller report of November, 2003 McElroy advised Markland, as a
result of a further inspection from the No. 5 side, that there was contact between No. 5 and No. 70 at foundation level which was
contrary to what was originally intended and that there was no evidence of a compressible board (Korpak) between the two
foundations, as McElroy had detailed.
5. In the substantive proceedings the plaintiff claimed damages against Markland for breach of an agreement between the respective
architects of Markland and the plaintiff on their principals’ behalf to maintain a gap of between 100 mm and 150 mm between No. 5
and the building on No. 70, and for negligence and breach of duty, and for trespass and nuisance. The claim against Cantier was for
damages for loss occasioned by its negligence, breach of duty, trespass and nuisance.
6. The voluntary winding up of Cantier commenced on 3rd July, 2003. Thereafter, until May, 2004, Cantier did not participate in the
proceedings. On 15th December, 2004 the plaintiff obtained judgment in default of defence against Cantier and the damages to which
the plaintiff was entitled were directed to be assessed. Subsequently, on 6th May, 2004 Cantier, on disclosure to the court that it
was defending through an indemnifier, was given liberty to deliver a defence. In its defence, which was delivered on 10th May, 2004,
the second defendant denied that the plaintiff had suffered any loss and pleaded contributory negligence on his part in failing to
minimise his loss.
7. The trial of the plaintiff’s action commenced on 19th October, 2004. As regards the position of the defendants inter se, on 28th
August, 2003 Markland had served notice claiming indemnity or contribution on Cantier and on 12th May, 2004 Cantier had served
notice claiming indemnity or contribution on Markland. At the hearing of the action the court was told that it had been agreed by the
parties that the issues between the defendants should be left in abeyance until the issues between the plaintiff and the defendants
were determined. Judgment was delivered on the plaintiff’s claim on 1st December, 2004. Because of the judgment in default of
defence, the liability of Cantier was not at issue. In relation to liability on the part of Markland, it was held that Markland had failed to
observe good building practice in installing the foundation of No. 70 and thereby breached the duty of care it owed to the plaintiff as
the adjoining property owner. It was also held that the agreement between the architects as to the maintenance of a gap between
the two buildings had not been implemented. Having addressed the issue as to damage caused to No. 5 by those breaches, the court
awarded the plaintiff damages in the sum of €238,909.90.
8. At the hearing of the action one witness only was called on behalf of Markland on the issue of liability, John Moylan of Moylan
Consulting Engineers and Project Managers, who was retained in February, 2004 in connection with the proceedings, if not earlier.
According to the evidence now put before the court by Markland, Markland continued to rely on the advices of McElroy in relation to
the merits of its case generally and McElroy personnel remained witnesses in the case, which I assume means potential witnesses
given that no member of the firm was called, and attended consultations, provided reports and generally assisted in addressing the
factual and technical issues which arose in the case.
9. The award of damages to the plaintiff has not been appealed by Markland. However, a subsequent judgment of the court, which
was delivered on 20th December, 2004, awarding costs to the plaintiff, which was the subject of a perfected order of 15th March,
2005, has been appealed.
10. Following the judgments of the court on the plaintiff’s claim, on 19th January, 2005 the solicitors for Markland wrote to McElroy
putting them on notice of certain facts, including that, should the insurers of Cantier fail to admit liability in full, members of McElroy
who would have been involved in the case would be essential witnesses to make the case that Cantier was entirely responsible for
the damage which occurred and to rebut whatever allegations of default on the part of Markland’s professional advisers might be
made by Cantier. It was stated that Markland was “an innocent party” in the whole affair and that it was Markland’s belief that no
finding of liability could be made against it unless the court made a finding that there was default on the part of Markland’s
professional advisers, which contributed to the damage to No. 5. McElroy was notified that, in the event of the High Court
determining that there had been any default or failure on the part of Markland’s professional advisers which created a liability on the
part of Markland, Markland would require the relevant professional advisers or their insurers to bear the costs of discharging such
liability in full, including all the costs of Markland and all other parties involved in the proceedings to the extent that they might not be
discharged by Cantier. It was suggested that, if McElroy had not already done so, it should notify its insurers of the letter. The
response of McElroy in a letter dated 26th January, 2005 was a statement of firm belief that McElroy had no liability in the case
arising from its services on the project.
11. The proceedings on the reciprocal claims for contribution or indemnity proceeded on the basis that Markland was the claimant and
Cantier the respondent. Points of claim were delivered by Markland on 17th February, 2005. Points of defence and counterclaim were
delivered by Cantier on 28th April, 2005. Notice seeking particulars arising from the points of defence and counterclaim were delivered
by Markland to Cantier on 10th May, 2005. Replies were not furnished until 23rd March, 2006.
12. In the interim, on 25th January, 2006 Markland issued a notice of motion on foot of which the order of 31st March, 2006 joining
McElroy as a third party was made. The motion was on notice to Cantier. On 30th January, 2006 Markland’s solicitors advised McElroy
that the application was pending.
13. Following the making of the order of 31st March, 2006 a third-party notice dated 27th April, 2006 was filed. On 28th April, 2006
Markland delivered amended points of claim against Cantier as first respondent and McElroy as second respondent. The claim for
indemnity or contribution against McElroy as pleaded is based on allegations of negligence and breach of duty and breach of contract
on the part of McElroy, in broad terms, in failing to give adequate instructions to Cantier in relation to ensuring separation of No. 5
and No. 70 at foundation level, failing to supervise the works adequately and failing to take steps to separate the buildings
subsequently.
14. A factual matter to which counsel for McElroy ascribed significance was information which Markland’s solicitors had in early July,
2003 following queries channelled through Niall Sheehan, the project manager of Markland, to Ian Guinness, the contracts manager for
Cantier. The information would appear to have been sought in connection with the defence of the plaintiff’s application for an
interlocutory injunction. It is not denied that Markland’s solicitors had information that Mr. Guinness’s view at the time was that the
foundations of No. 70 did touch the foundations of No. 5 for the full length of the foundation and that this was “as per the
construction detail issued by Jack O’Regan [of McElroy]” and that Mr. Guinness could say this because he saw the excavated
foundation on 18th December, 2002. Mr. Guinness had answered a question whether he could confirm that the new building was built
in accordance with the engineers’ designs by stating “in principle, yes”, but he would need to see a copy of the drawings as issued
for construction to swear to that fact.
The law
15. There was really no dispute between counsel for McElroy and counsel for Markland as to the legal principles by reference to which
an application to set aside third-party proceedings should be determined where, as here, the basis of the application is that the third-
party notice was not served in time.
16. Order 16, r. 1(3) of the Rules of the Superior Courts, 1986 provides that application for leave to issue a third-party notice shall,
unless otherwise ordered by the court, be made within 28 days from the time limited for delivering the defence or, where the
application is made by the defendant to a counterclaim, the reply. It was held by the Supreme Court in Board of Governors of St.
Laurence’s Hospital v. Staunton [1990] 2 I.R. 31 that that provision and the discretion vested in the court by it must be exercised
subject to the statutory provisions which give rise to the jurisdiction, namely, s. 27(1)(b) of the Civil Liability Act, 1961. Sub-section
(1) of s. 27 provides:
“A concurrent wrongdoer who is sued for damages or for contribution and who wishes to make a claim for contribution
under this Part –
(a) …
(b) shall, if the said person is not already a party to the action, serve a third-party notice upon such person as
soon as is reasonably possible and, having served such notice, he shall not be entitled to claim contribution except
under the third-party procedure. If such third-party notice is not served as aforesaid, the court may in its
discretion refuse to make an order for contribution against the person from whom the contribution is claimed.”
17. As to the construction of that provision, Finlay C.J. stated as follows (at p. 36):
“I am satisfied upon the true construction of that sub-section that the only service of a third-party notice contemplated
by it and, therefore, the only right of a person to obtain from the High Court liberty to serve a third-party notice claiming
contribution against a person who is not already a party to the action, is a right to serve a third-party notice as soon as
is reasonably possible. A defendant in an action seeking to claim contribution against a person who is not a party to the
proceedings cannot serve any third-party notice at any other time, other than as soon as is reasonably possible.”
18. The rationale of the provision was considered by the Supreme Court in Molloy v. Dublin Corporation [2001] 4 I.R. 52. Murphy J.,
with whom the other judges agreed, stated as follows (at p. 55):
“There can be little doubt as to what that scheme and purpose was. The legislature was understandably desirous of
avoiding a multiplicity of actions. Instead of defendants against whom awards had been made instituting further
proceedings against other parties liable to them in respect of the same set of facts – and indeed those defendants in turn
perhaps instituting even more proceedings against others – the Oireachtas sought to establish a situation in which the
rights and liabilities of all parties arising out of a particular set of circumstances would be disposed of in the same
proceedings. … Nevertheless, the legislature did not preclude an unsuccessful defendant in the original proceedings from
instituting a substantive action against some other party who the actual defendant contended was liable to him either in
tort or in contract. What the Act of 1961 did provide was that where the actual defendant in the original proceedings
failed to avail of the third-party procedure by serving the third-party notice ‘as soon as is reasonably possible’ and
resorted to his original cause of action, the relief which he might have claimed therein was subject to the statutory
discretion of the court to refuse to make an order for contribution in his favour.”
19. The discretion referred to is the discretion conferred in the last sentence of para. (b) of s. 27(1).
20. As to the meaning of “as soon as is reasonably possible”, having quoted the passage from the judgment of Finlay C.J. quoted
earlier, Murphy J. continued (at p. 56):
“The terms in which the time was expressed do appear severe. The use of the word ‘possible’ rather than the word
‘practicable’, as is invoked elsewhere, suggests a brief and inflexible time limit. It might suggest that if it is physically
possible to serve the appropriate notice within the identified period, that any further delay would be impermissible.
However, such a draconian approach would be inconsistent with the nature of the problems to be confronted by a
defendant and of the decisions to be made by him or his advisers. The statute is not concerned with physical possibilities
but legal and perhaps commercial judgments. Proceedings cannot and should not be instituted or contributions sought
against any party without assembling and examining the relevant evidence and obtaining appropriate advice thereon. It is
in that context that the word ‘possible’ must be understood. Furthermore, the qualification of the word ‘possible’ by the
word ‘reasonable’ gives a further measure of flexibility. As Barron J. pointed out in McElwaine v. Hughes (Unreported, High
Court, Barron J., 30th April, 1997) at p. 6 of the unreported judgment:-
‘Clearly the words “as soon as reasonably possible” denote that there should be as little delay as possible,
nevertheless, the use of the word “reasonable” indicates that circumstances may exist which justify some delay in
the bringing of the proceedings.’”
21. Suggesting that the claim against McElroy is akin to a claim for professional negligence, counsel for Markland place particular
reliance on the judgment of the Supreme Court in Connolly v. Casey [2000] 1 I.R. 345. In that case the defendants, being solicitors
against whom the plaintiff was seeking damages for professional negligence, although having delivered a defence on 22nd April, 1996
in which they had pleaded negligence and breach of duty on the part of the third party, a barrister, in respect of advice he had given,
awaited the delivery of replies to particulars sought and advanced that as one of the explanations for not having obtained leave to
issue and serve a third-party notice until 20th October, 1997 on foot of a motion issued on 25th July, 1997. The Supreme Court
reversed the decision of the High Court to set aside the third-party proceedings. In her judgment, with which the other judges
agreed, Denham J. stated that the wrong test had been applied at first instance and continued (at p. 350):
“The test is whether it was reasonable to await the replies to particulars. Whether the replies did or did not materially
alter the defendants’ state of knowledge is not the test. The queries raised in the notice for particulars were relevant to
the claim against the third party and thus it was reasonable to await the replies.”
22. Denham J. also held that it was not unreasonable for the solicitors conducting the defence, presumably on behalf of an
indemnifier, to have sought a statement from the solicitor who had briefed the third-party barrister and to have awaited its arrival. In
this connection, Denham J. observed (at p. 350):
“It is important in professional negligence cases to act reasonably. Proceedings must have an appropriate basis. Counsel
have a duty of care. Reference has already been made to the need to develop modern case management in cases relating
to professional negligence: Cook v. Cronin (Unreported, Supreme Court, 14th July, 1999).”
23. Later in her judgment, Denham J. set out the approach which should be adopted to analysing delay in the context of s. 27(1)(b)
and stated as follows:
“In analysing the delay – in considering whether the third-party notice was served as soon as is reasonably possible – the
whole circumstances of the case and its general progress must be considered. The clear purpose of the sub-section is to
ensure that a multiplicity of actions is avoided: see Gilmore v. Windle [1967] I.R. 323. It is appropriate that third-party
proceedings are dealt with as part of the main action. A multiplicity of actions is detrimental to the administration of
justice, to the third party and to the issue of costs. To enable a third party to participate in the proceedings is to
maximise his rights. He is not deprived of the benefit of participating in the main action.”
24. Counsel for McElroy submitted that Denham J. emphasised that the decision was specific to the facts before the court, and was
not to be seen as diluting the requirements of s. 27(1)(b), in the following passage at 352:
“In conclusion, I would allow the appeal of the defendants on the grounds that the delay of the defendants was not
unreasonable and that in the circumstances of the case the third-party notice was served ‘as soon as is reasonably
possible’. However, this is a case with particular facts in a suit alleging professional negligence and the decision does not
endorse delay – rather it seeks to encourage a modern management of litigation to avoid a multiplicity of suits.”
25. It is well settled that on an application to set aside third-party proceedings, the onus of proof of showing that the delay at issue
was not unreasonable is on the defendant.
26. While arguing that it is not necessary for the applicant to establish prejudice, it was submitted on behalf of McElroy that, where it
is present, the court should be all the more willing to strike out the third-party proceedings. As the commentary in Delany & McGrath
on Civil Procedure in the Superior Courts, 2nd Edition, at paras. 9-18 and 9-19 indicates, there is something of a divergence of opinion
on the authorities as to the relevance of prejudice, in that in Ward v. O’Callaghan (Unreported, High Court, Morris P., 2nd February,
1998) Morris P. appeared to countenance consideration of prejudice, whereas Kelly J. in S.F.L. Engineering Limited v. Smyth Cladding
Systems Limited [1997] IEHC 81 (9th May, 1997) stated at para. 12:
“In considering applications of this sort, the court is not concerned with any question of prejudice arising as a result of
the delay in applying for liberty to join the third party. This was accepted by counsel appearing on behalf of the
defendants in the present case and it seems to follow from the interpretation given to the relevant provision by Finlay
C.J. in the St. Laurence’s Hospital case.”
27. Section 27(1)(b) makes the service of a third-party notice “as soon as is reasonably possible” mandatory. In my view, the
absence or presence of special prejudice affecting the proposed third party is not something the court is required to have regard to in
determining whether the third-party proceedings are valid. Apart from that, in my view, it would be inherently dangerous for a court
on an application to set aside third-party proceedings to examine, and express a view on, the type of issues which it is asserted
constitute special prejudice affecting McElroy in this case, where the entitlement of the unsuccessful defendant, in this case,
Markland, to institute a substantive action against the third party remains, even if the third party proceedings are set aside.
Application of the law to the facts - submissions
28. McElroy argued that the third-party notice was not served as soon as was reasonably possible on two alternative bases. The first
was that McElroy should have been brought in as a third-party before the trial of the action between the plaintiff and the defendants
so that it could have participated in that trial. The alternative argument was that, even if Markland was entitled to await the
outcome of the trial of the plaintiff’s claim against the defendants, there was unreasonable and unexplained delay between the
service of Cantier’s points of defence and counterclaim on 28th April, 2005 and the service of the third-party notice twelve months
later and, even the issue of the third-party application some nine months later.
29. Counsel for McElroy submitted that support for the proposition that Markland should have brought in McElroy as a third party
when it became aware of the claim being made against it by the plaintiff is to be found in the decision of the Supreme Court in the St.
Laurence’s Hospital case. The facts in that case were that the plaintiff had been admitted to St. Laurence’s Hospital under the care
of Mr. Staunton, a consultant neurologist. In July, 1981 he fell from a window in the hospital and sustained serious injuries. In
September, 1983 he issued a plenary summons in the High Court against the defendant hospital. The statement of claim was filed in
November, 1983 and replies to the defendant’s notice for particulars of negligence were delivered in July, 1984. A full defence was
filed and the action was set down for trial in 1985. It was heard in July, 1987, during which Mr. Staunton was called as a witness for
the defendant. At the conclusion of the trial the jury awarded the plaintiff £90,000. The defendant appealed on liability and quantum
and the appeal was ultimately dismissed. However, while the appeal was pending, the defendant obtained an order for liberty to serve
a third-party notice on Mr. Staunton. On those facts, Finlay C.J. concluded that the serving of a third-party notice on the third party
after the conclusion of the plaintiff’s claim was not serving it as soon as reasonably possible. He stated (at p. 36):
“In my view, the application brought after the conclusion of the action by the plaintiff against the defendants for liberty
to serve a third-party notice could not, under any circumstances, be construed as an application to serve a third-party
notice as soon as was reasonably possible. It is clear from the facts which I have outlined that probably from the month
of July, 1984, when particulars were filed, the defendants were aware of the nature of the claim which was being brought
against them by the plaintiff. They may have been unaware as to whether that claim would succeed or not, but they
were aware of what the nature of the claim was, and it must follow, it seems to me, that they were also aware at the
time of any potential claim for contribution they might have against the third party.”
30. In this case, McElroy contends, Markland was in a position to consider and decide whether a claim for contribution arose against it
at the latest towards the end of 2003. By September, 2003 it was common knowledge that there was no separation joint between
No. 70 and No. 5 at foundation level. That, of itself, was sufficient to put Markland on notice of a potential claim, which clearly
warranted immediate investigation and inquiry, it was submitted. McElroy went further and submitted that the existence of the e-mail
suggests that Markland was aware that the position Cantier would adopt was that the foundations as constructed were in
accordance with the construction details issued by McElroy. It was submitted that Markland’s strategy, as is to be gleaned from the
letter of 19th January, 2005 from its solicitors, was that Markland was prepared to allow the plaintiff’s claim to proceed to a hearing
on the basis that, if it was found by the court that the absence of a separation joint did cause structural damage to No. 5, it could
pursue a claim against one or more of its professional advisers, including McElroy, after the court determination. It was submitted that
that was an inappropriate approach, in that it prevented McElroy from deciding whether to participate in the trial of the plaintiff’s
action or to elect to have the claim for indemnity or contribution against it held over. Joinder of McElroy as a third party would have
avoided a multiplicity of proceedings.
31. On the alternative argument, it was submitted on behalf of McElroy that Markland could have taken steps to compel Cantier to
reply to the notice for particulars dated 10th May, 2005. It was further submitted that, in any event, the particulars ultimately
furnished on 23rd March, 2006 had no relevance because they post-dated the decision to seek to join McElroy as a third party.
32. Markland’s explanation for not seeking to join McElroy as a third party prior to the determination of the action between the
plaintiff and the defendants was that there was no allegation against McElroy by Cantier until after the determination of that action.
Its explanation for not having moved more expeditiously after receipt of Cantier’s defence and counterclaim was that, because of the
lack of clarity in Cantier’s pleading, it was necessary for Markland to seek particulars from Cantier and to engage in its own process of
investigation to ascertain whether it has a claim against McElroy. If it had not adopted that approach, it was submitted, the
consequence might have been the joinder of a multiplicity of parties because the allegations made by Cantier implicated not merely
McElroy but also Markland itself and its architects. On the authorities (Connolly v. Casey and Cook v. Cronin) Markland was obliged to
identify the existence of a clear cause of action before initiating proceedings against its professional advisers for professional
negligence, it was submitted.
33. Markland also sought to attach some significance to Cantier’s limited participation in the plaintiff’s action because it was in
liquidation at the time of the discovery, in September, 2003, of the absence of a separation joint at foundation level between No. 70
and No. 5 and to the fact that, when its participation was permitted in May, 2004, it did not deny liability. Of course, it could not
have denied liability because of the existence of the judgment. As I understand Markland’s argument, it is that, given those
circumstances, Markland could not reasonably be expected to have concluded that some fault was then, or could be, attributed to
McElroy by Cantier.
34. Counsel for McElroy countered this last point on the basis that it was nihil ad rem. The proposition that it is necessary for some
other party to make a specific allegation of wrongdoing against a prospective third party before an obligation exists to move speedily
and without delay to institute third-party proceedings, it was submitted, is not supported by authority.
Conclusions
35. The issue which the court has to determine is whether Markland served the third-party notice dated 27th April, 2006 on McElroy
as soon as reasonably possible.
36. As was recognised in the affidavit of Aidan Scully sworn on 25th January, 2006, which grounded Markland’s application for leave
to serve the third-party notice on McElroy, the principal issue as between the plaintiff and the defendants was the failure to achieve
separation between No. 70 and No. 5. The absence of a separation joint at foundation level between the two properties was common
knowledge from September, 2003. The plaintiff’s contention was that that factor had caused, and probably would in the future cause,
structural damage to No. 5. While Markland put in issue the existence of damage and causation, it must have been obvious to it that,
if the court were to find that structural damage existed and that it was caused by the absence of the separation joint, to adopt the
terminology adopted by Finlay C.J. in the St. Laurence’s Hospital case, there was a potential claim for contribution against McElroy,
on the basis that the absence of the separation joint must have been attributable either to Cantier not having followed McElroy’s
instruction or McElroy having given no instructions to ensure separation of the two buildings at foundation level. It was at that stage
that Markland should have conducted an investigation of the role of McElroy, which was the retained professional responsible for the
structural aspects of the building operations on the site of No. 70, with a view to assessing whether it was appropriate to seek leave
to join McElroy. The evidence indicates that it would have been reasonably possible to make the necessary professional judgment by
the end of 2003.
37. The fact that Cantier’s participation in the plaintiff’s action was dormant between July, 2003 and May, 2004 and the fact that its
defence of the plaintiff’s claim was circumscribed by the existence of the judgment in default of defence, are not matters which
justify Markland’s failure to pursue a claim for contribution against McElroy until after the conclusion of the plaintiff’s claim. Nor does
the fact that Cantier did not articulate that the construction of No. 70 at foundation level without a separation joint was carried out
on the express instructions of Markland, its servants or agents, including, McElroy until 28th April, 2005 justify that failure. It was the
plaintiff’s claim against Markland and Cantier for damages which triggered the obligation under s. 27(1)(b) of each of the defendants
to serve a third-party notice if either wished to claim a contribution against a non-party, not the formal pleading of the defendants’
claims for indemnity and contribution inter se.
38. The approach adopted by Markland in this case with the concurrence of Cantier has given rise to, not obviated, a multiplicity of
actions. The trial of the plaintiff’s claim against both defendants took place over twelve days in 2004. The fact that the issues
between the defendants were left over means that there will be a second trial to determine those issues. Even if the court were to
reject McElroy’s application to set aside the third-party proceedings, a beneficial outcome to the system of administration of justice
and to the third party of the type envisaged by Denham J. in Connolly v. Casey cannot be achieved here.
39. For the foregoing reasons, I consider that the third-party notice was not served as soon as reasonably possible and, therefore,
the third-party proceedings must be set aside. I am not oblivious to the fact that this decision may result in a third trial: the trial of a
substantive action by Markland against McElroy. Whether, in that event, the court should exercise its discretion to refuse to make an
order for contribution, as provided for in the last sentence of para. (b) of s. 27(1), is a matter for another day.
Order
40. There will be an order setting aside the third-party proceedings.