Supreme Administrative Court allows compensation for construction delays caused by nature protection ban under section 18(2).
Legislator-Zusammenfassung
KI-generiertThe Supreme Administrative Court ruled that construction costs incurred due to delays caused by a nature protection ban must be compensated. The applicants argued they had met construction deadlines before the ban and intended to use or rent the buildings during the ban period. The court held that these specific costs qualify for compensation under the relevant nature protection law provision.
Legislator-Regeste
KI-generiertLuonnonsuojelulain 18 § 2 mom; Costs incurred by applicants due to construction delays caused by a nature protection ban are compensable if the applicants were able to complete construction before the ban and intended to use the buildings during the ban period.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVerwandte Entscheide
KI-generiertVolltext
Hakijat olivat alueelle luonnonsuojelulain 18 §:n 2 momentin nojalla määrätyn toimenpidekiellon voimassaoloaikana estyneet käyttämästä kiinteistöjään heille ennen toimenpidekiellon antamista myönnettyjen rakennuslupien mukaiseen lomarakentamiseen. Tästä rakentamisen viivästymisestä hakijoille aiheutuneita kustannuksia, ottaen huomioon, että hakijat olisivat kiellon voimassaoloaikana ehtineet rakentaa lomarakennukset ja käyttää niitä itse tai vuokrata rakennukset ainakin osaksi kiellon voimassaoloaikaa, oli pidettävä laadultaan sellaisina kustannuksina, jotka mainitun säännöksen mukaan oli hakijoille korvattava.
LuonnonsuojeluL 18 § 2 mom (71/23)