Court allows delay in coastal protection works before water discharge increase if not unreasonably delaying the project.
Legislator-Zusammenfassung
KI-generiertThe Administrative Court allowed the Water Authority to delay coastal protection works until after increasing the water discharge capacity. The Authority argued that performing protection first would unreasonably delay the project, while the opposing party contended that protection should precede the discharge increase to prevent damage. The court ruled that since the delay was not unreasonable and the protection was necessary, the established order of operations did not need to be followed in this specific instance.
Legislator-Regeste
KI-generiertVesiL 11 luku 14a ) 2 mom; VesiL 11 luku 13: The general rule requiring compensation before action does not strictly apply when protective measures can be reasonably delayed without causing undue harm to the project timeline.
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVerwandte Entscheide
KI-generiertVolltext
VEO oli määrännyt voimalaitoksen rakennusvirtaaman nostamisluvassa,
että rantojen suojaustyöt oli tehtävä ennen rakennusvirtaaman
nostamista.
VYO ei muuttanut tältä osin VEO:n päätöksen lopputulosta. VL
11:14a,2:n mukaan rahakorvaus on pääsääntöisesti suoritettava
ennen korvausvelvollisuuden aiheuttavaan toimenpiteeseen ryhtymistä.
VYO katsoi, että rannan suojaukseen, jolla estettiin
toimenpiteestä aiheutuvan vahingon syntyminen, oli periaatteessa
sovellettava samaa järjestystä. Rantojen suojaaminen
ennen rakennusvirtaaman nostamista ei tässä tapauksessa kohtuuttomasti
viivästyttänyt hanketta ja oli tarkoituksenmukaista.
Asiassa ei ollut syytä poiketa edellä mainitusta ilmenevästä
järjestyksestä.
VesiL 11 luku 13 )
VesiL 11 luku 14a ) 2 mom
KHO:ssa