Appeal Dismissed for Procedural Non-Compliance in Agricultural Land Construction Case
Legislator-Zusammenfassung
KI-generiertThe appeal was dismissed as inadmissible due to the appellant's failure to collaborate, which is a procedural requirement under the relevant administrative procedure law concerning a situation involving construction and installation on agricultural land that resulted in a fine.
Legislator-Regeste
AmtlichPROCEDURE ADMINISTRATIVE; CONSTRUCTION ET INSTALLATION; ZONE AGRICOLE; TERRAIN; AMENDE; DEVOIR DE COLLABORER; TPE | Recours rejeté vu le défaut de collaboration du recourant (8 CCS). | LPA.24 al.2
Schlagwörter
KI-generiertZitierte Gesetzesbestimmungen
KI-generiertVerwandte Entscheide
KI-generiertZentrale Rechtsfragen, extrahiert von Legislator
KI-generiertThe appeal was rejected based on the lack of cooperation by the appellant.
Volltext
A/408/1997
### [ATA/591/1997](/apps/decis/fr/ata/show/1875074) du 30.09.1997 ( TPE ) , IRRECEVABLE Descripteurs : PROCEDURE ADMINISTRATIVE; CONSTRUCTION ET INSTALLATION; ZONE AGRICOLE; TERRAIN; AMENDE; DEVOIR DE COLLABORER; TPE Normes :
LPA.24 al.2
Parties : DI PADOVA Nicola / DEPARTEMENT DES TRAVAUX PUBLICS ET DE L'ENERGIE Résumé : Recours rejeté vu le défaut de collaboration du recourant (8 CCS).
Pas de document HTML